Questions

Q:

After the initial success of the Revolt of 1857, the objective for which the leaders of the Revolt worked was

A) to restore the former glory to the Mughal empire B) to form a Federation of Indian States under the aegis of Bhadur Shah II
C) elimination of foreign rule and return of the old order D) each leader wanted to establish his own power in his respective region
 
Answer & Explanation Answer: C) elimination of foreign rule and return of the old order

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History

1 5036
Q:

What is seismic zone extending at an angle of about 45 degrees from the base of an ocean trench, down through lithosphere to the asthenosphere known as

A) Appleton layer B) Benioff zone
C) Conard discontinuity D) Convergence zone
 
Answer & Explanation Answer: B) Benioff zone

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Geography

1 5036
Q:

Where is the Rail Wheel Factory situated

A) Srirangpattam B) Gulbarga
C) Hampi D) Yelahanka
 
Answer & Explanation Answer: D) Yelahanka

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Economy

3 5036
Q:

As you go down into a well, your weight 

A) increases slightly B) decreases slightly
C) remains exactly the same D) none of these
 
Answer & Explanation Answer: B) decreases slightly

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Science

18 5034
Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 5029
Q:

In which categories did Marie Curie win her two different Nobel Prizes

A) Physics and chemistry B) Chemistry and Medicine
C) Physics and Medicine D) Chemistry and Peace
 
Answer & Explanation Answer: A) Physics and chemistry

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Honours and Awards

3 5029
Q:

Who is known as "Iron Lady of India"? 

A) Rani Laxmi Bai B) Sonia Gandhi
C) Indira Gandhi D) None of the above
 
Answer & Explanation Answer: C) Indira Gandhi

Explanation:

Indira Gandhi the first Prime Minister of India is known as the Iron Lady of India.

Who_is_known_as_Iron_Lady_of_India1542609309.jpg image

Report Error

View Answer Report Error Discuss

Filed Under: Indian History
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

9 5026
Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 5025