A Woman’s downstream swimming rate is thrice of her upstream swimming rate. If she covers 12 km upstream in 2.5 hours, what distance she will cover in 5 hours downstream?

 

A) 72 km B) 36 km
C) 56 km D) 42 km
 
Answer & Explanation Answer: A) 72 km

Explanation:

Rate of her upstream = 12/2.5 = 4.8 km/hr

Then, ATQ

Rate of downstream = 4.8 x 3 = 14.4 km/hr

 

Hence, the distance she covers downstream in 5 hrs = 14.4 x 5 = 72 kms.

Report Error

View Answer Report Error Discuss

Filed Under: Boats and Streams
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

17 4761
Q:

I learnt from my experience that by______ my anger and resentment, and by avoiding _________ I could overcome opponents more successfully than could those who openly defied their adversaries.

A) suppressing, conflict B) expressing, hostility
C) stifling, temperance D) rousing, wrath
 
Answer & Explanation Answer: A) suppressing, conflict

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Analogy
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE , TOEFL
Job Role: Bank Clerk , Bank PO

6 4750
Q:

1 Billion Seconds Equals to

A) 34.76 years B) 32.48 years
C) 33.31 years D) 31.68 years
 
Answer & Explanation Answer: D) 31.68 years

Explanation:

We know that 1 year = 365.25 days

1 day = 24 hours

1 hour = 60 minutes

1 minute = 60 seconds

 

=> 1 Year = 365.25 x 24 x 60 x 60 Seconds

But 1 billion seconds = ?

1 Year = 365.25 x 24 x 60 x 60 Seconds

    ?     =  1000000000 Seconds

 

? = 1000000000365.25 x 24 x 60 x 60 years = 31. 68 years.

 

Report Error

View Answer Report Error Discuss

37 4749
Q:

Which among the following is not aprocess state in unix?

A) Running B) Runnable
C) Zombie D) Stopped
 
Answer & Explanation Answer: B) Runnable

Explanation:

The process states of unix are running,Zombie,stopped,Waiting.

Report Error

View Answer Report Error Discuss

Filed Under: Operating Systems
Exam Prep: GATE

7 4744
Q:

A watch which gains uniformly is 2 minutes low at noon on Tuesday and is 4 min 48 sec fast at 2 p.m. on the following Tuesday. When was it correct ?

A) 12 p.m. on Wednesday B) 2 p.m. on Thursday
C) 3 p.m. on Thursday D) 2 p.m. on Wednesday
 
Answer & Explanation Answer: B) 2 p.m. on Thursday

Explanation:

Time from 12 p.m. on Tuesday to 2 p.m. on the following Tuesday = 7 days 2 hours.
= 170 hours.
The watch gains = (2 + 4 x 4/5) min
= 34/5 min. in 170 hrs.
Now, 34/5 min are gained in 170 hrs.
Then, 2 min are gained in (170 x 5/34 x 2) hrs.
Watch is correct after 2 days 2 hrs after 12 p.m. on Tuesday, i.e., it will be correct at 2 p.m. on Thursday.

Report Error

View Answer Report Error Discuss

Filed Under: Clocks
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Analyst , Bank Clerk , Bank PO , Network Engineer , Project Manager

9 4743
Q:

Carbon monoxide is a common atmospheric pollutant.

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:

Carbon monoxide is one of the major pollutant present in the world. The six most common pollutants include ozone, carbon monoxide, sulfur dioxide, lead, nitrogen oxides, and particulate matter.


 


Carbon monoxide is a common atmospheric pollutant. It is produced largely in combustion processes like in industries and in vehicles. It is a gas that cannot be seen nor smelled.

Report Error

View Answer Workspace Report Error Discuss

Subject: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

1 4737
Q:

Find the Odd one out of the following Numbers?

A) 3 B) 19
C) 67 D) 133
 
Answer & Explanation Answer: D) 133

Explanation:

Here among the given numbers, 3, 19, 67 are prime numbers. And 133 is not a prime number.

 

Hence, the odd number of the given numbers is 133.

Report Error

View Answer Report Error Discuss

4 4732
Q:

A,B,C can complete a work in 15,20 and 30 respectively.They all work together for two days then A leave the work,B and C work some days and B leaves 2 days before completion of that work.how many days required to complete the whole work?

Answer

Given A,B,C can complete a work in 15,20 and 30 respectively.


The total work is given by the LCM of 15, 20, 30 i.e, 60.


A's 1 day work = 60/15 = 4 units


B's 1 day work = 60/20 = 3 units


C's 1 day work = 60/30 = 2 units


(A + B + C) worked for 2 days = (4 + 3 + 2) 2 = 18 units


 Let B + C worked for x days = (3 + 2) x = 5x units


C worked for 2 days = 2 x 2 = 4 units


Then, 18 + 5x + 4 = 60


22 + 5x = 60


5x = 38


x = 7.6


 


Therefore, total number of days taken to complete the work = 2 + 7.6 + 2 = 11.6 = 11 3/5 days.