GATE Questions

Q:

45 men working 9 hours per day dig 40 m deep. How many extra men should be put to dig to a depth of 56 m working 7 hours per day ?

A) 36 B) 61
C) 48 D) 54
 
Answer & Explanation Answer: A) 36

Explanation:

(45 x 9)/40 = (M x 7)/56 => M = 81

=> 81 – 45 = 36

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

6 8899
Q:

How much time will a train of length 200 m moving at a speed of 72 kmph take to cross another train of length 300 m, moving at 36 kmph in the same direction ?

A) 58 sec B) 62 sec
C) 60 sec D) 50 sec
 
Answer & Explanation Answer: D) 50 sec

Explanation:

The distance to be covered = Sum of their lengths = 200 + 300 = 500 m.

Relative speed = 72 -36 = 36 kmph = 36 x 5/18 = 10 mps.

Time required = d/s = 500/10 = 50 sec.

Report Error

View Answer Report Error Discuss

Filed Under: Problems on Trains
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Analyst , Bank Clerk , Bank PO

8 8887
Q:

egg: fish : : ________ : plant

A) seed B) stem
C) root D) leaf
 
Answer & Explanation Answer: A) seed

Explanation:

Fish is from eggs whereas plant is from seeds.

Report Error

View Answer Report Error Discuss

Filed Under: Analogy
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE , TOEFL
Job Role: Bank Clerk , Bank PO

9 8876
Q:

Crack this Logical thinking Math Puzzle?

logic_puzzle1533711581.jpg image

A) 9 B) 8
C) 7 D) 6
 
Answer & Explanation Answer: B) 8

Explanation:

Here by observing the figure, 

we can complete the above incomplete cube with 2 cubes in 2 rows and 2 columns

=> 2 x 4 = 8.

 

Hence, with 8 small cubes we can complete the cube.

Report Error

View Answer Report Error Discuss

Filed Under: Math Puzzles
Exam Prep: GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

26 8836
Q:

50 men can build a tank in 40days, but though they begin the work together, 5 men quit every ten days. The time needed to build the tank is ?

A) 50 days B) 48 days
C) 47.5 days D) 49 days
 
Answer & Explanation Answer: A) 50 days

Explanation:

50 men can build a tank in 40 days 

Assume 1 man does 1 unit of work in 1 day

Then the total work is 50×40 = 2000 units

 

50 men work in the first 10 days and completes 50×10 = 500 units of work

45 men work in the next 10 days and completes 45×10 = 450 units of work

40 men work in the next 10 days and completes 40×10 = 400 units of work

35 men work in the next 10 days and completes 35×10 = 350 units of work

So far 500 + 450 + 400 + 350 = 1700 units of work is completed and

 

Remaining work is 2000 - 1700 = 300 units

 

30 men work in the next 10 days. In each day, they does 30 units of work.

 

Therefore, additional days required = 300/30 =10

 

Thus, total 10+10+10+10+10 = 50 days required.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams
Job Role: Bank PO , Bank Clerk

12 8830
Q:

Tractor : Trailer :: Horse : ?

A) Saddle B) Engine
C) Cart D) Stable
 
Answer & Explanation Answer: C) Cart

Explanation:

Here the given words are related in such a way that,

Trailer is pulled by Tractor and similarly, Cart is pulled by Horse.

 

Hence, Tractor : Trailer :: Horse : Cart.

Report Error

View Answer Report Error Discuss

Filed Under: Analogy
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO , Database Administration , IT Trainer

13 8819
Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days 

=> 1 day work of X = 1/10

 

Y can do in 15 days 

=> 1 day work of Y = 1/15

 

1day work of (X + Y) = 1/10 + 1/15 = 1/6

 

Given they are hired for 5 days

 => 5 days work of (X + Y) = 5 x 1/6 = 5/6

 Therefore, Unfinished work = 1 - 5/6 = 1/6 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

11 8816
Q:

Four thermal heaters A,B, C and D are used in the R & D department of Raliance chemicals Ltd. Only one heater can be used on any day . If heater A is used on any day, neither A nor C can be used the next day. If heater C is used on any day, neither C nor D can be used on the next day. If heater C is used on any day, then A has to be used the next day. If heater D is used on any day, then B has to be used the next day.

If heater D is used on the third day and different heaters are used on first and fourth day, which heater is used on the first day ?

   (1) D       (2) A       (3) B        (4) C

Answer

If heater D is used on the third day, heater B has to be used on the fourth day and A has to be used on the second day. But if A is used on second day, then either B or C has to be used on the first day. But if heater B is used on the first day, then according to the question, the requirement of having different heaters on the first day and fourth days would not be fulfilled. Hence the heater that would be used on the first day is C.

Report Error

View answer Workspace Report Error Discuss

7 8815