PMP Certification Questions

Q:

Organizational Systems

What are Project-based and Non project-based organizations?

Answer



      • Project-based Organizations are those whose operations consist primarily of projects.

      • Non Project-based organizations often may lack management systems designed to support project needs efficiently and effectively.



Report Error

View answer Workspace Report Error Discuss

0 2195
Q:

Project Quality Management

What are the Project Management Processes included in the Project Quality Management?

Answer

Quality planning - Identifying which quality standards are relevant to the project and determining how to satisfy them


Perform Quality Assurance - Applying the planned , systematic quality activities to ensure that the project employs all processes needed to meet requirements.


Perform Quality Control - monitoring specific project results to determine whether they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance.

Report Error

View answer Workspace Report Error Discuss

0 2188
Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Select Sellers?

Answer

I. Inputs



  • Organizational process assets

  • Procurement management plan

  • Evaluation criteria

  • Procurement document package

  • Proposals

  • Qualified sellers list

  • Project management plan


                 - Risk register


                 - Risk related contractual agreements


II. Tools and Techniques



  • Weighting system

  • Independent estimates

  • Screening system

  • Contract negotiation

  • Seller rating systems

  • Expert judgment

  • Proposal evaluation techniques


III. Outputs



  • Selected sellers

  • Contract

  • Contract management plan

  • Resource availability

  • Procurement management plan (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2180
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Integrated Change Control Phase?

Answer

I. Inputs



  • Project management plan

  • Requested changes

  • Work performance information

  • Recommended preventive actions

  • Recommended corrective actions

  • Recommended defect repair

  • Deliverables


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Approved change requests

  • Rejected change requests

  • Project management plan(updates)

  • Project scope statement (updates)

  • Approved corrective actions

  • Approved preventive actions

  • Approved defect repair

  • Validated defect repair

  • Deliverables 

Report Error

View answer Workspace Report Error Discuss

0 2078
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Close project Phase?

Answer

I. Inputs



  • Project management plan

  • Contract documentation

  • Enterprise environmental factors

  • Organizational process assets

  • Work performance information

  • Deliverables


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Administrative closure procedure

  • Contract closure procedure

  • Final product, service, or result

  • Organisational process assets (updates)

Report Error

View answer Workspace Report Error Discuss

0 2078
Q:

Clossing Process Group

What are the Project Management Processes included in Closing Process Group?

Answer


    • Close Project

    • Contract Closure



 

Report Error

View answer Workspace Report Error Discuss

0 2040
Q:

Importance of project life cycle?

Answer

A project has a beginning and an end and passes through several phases of development known as life cycle phases. Every project has certain phases of development. A clear understanding of these phases allows managers and executives to maintain control of the project more efficiently.
These phases are varied depending upon the industry involved but all follow the same basic steps.


 


How Important is Project Life Cycle::


1. This is a tried and tested method for delivering projects on time, within budget and to the expected quality targets.


2. Aids communication and helps define roles within the project organisation as it provides a framework for the project that is visible and understood by all members of the project.


3. The project lifecycle will allow the project manager to link progress directly to each phase and recognise the completion of each phase


4. The phases within the project lifecycle provide an understanding of the evolution of the project, being able to identify areas that need greater attention at different times such as risk management in the early stages and more Project Evaluation Reviews during the Implementation stage.


5. At each stage, approval is generally required from outside the project team before proceeding to the next stage.


6. The project life cycle also allows for the gate procedure to be used.


7. At each stage, approval is generally required from outside the project team before proceeding to the next stage.

Report Error

View answer Workspace Report Error Discuss

6 2036
Q:

Planning Process Group

What are the Project Management Processes included in the Planning Process Group?

Answer



      • Develop Project Management Plan

      • Scope Planning

      • Scope Definition

      • Create WBS

      • Activity Definition

      • Activity Sequencing

      • Activity Resource Estimating

      • Activity Duration Estimating

      • Schedule Development

      • Cost Estimating

      • Cost Budgeting

      • Quality Planning

      • Human Resource Planning

      • Communications Planning

      • Risk Management Planning

      • Risk Identification

      • Qualitative Risk Analysis

      • Quantitative Risk Analysis

      • Risk Response Planning

      • Plan purchases and Acquisitions

      • Plan Contracting



Report Error

View answer Workspace Report Error Discuss

0 2034