PMP Certification Questions

Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Acquire Project Team?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Roles and responsibilities 

  • Project organization charts

  • Staffing management plan


II. Tools and Techniques



  • Pre-assignment

  • Negotiation

  • Acquisition

  • Virtual teams


III. Outputs



  • Project staff assignments

  • Resource availability

  • Staffing management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1898
Q:

Project Management Process Groups

What are the Project Management Process Groups?

Answer

This section identifies and describes the five Project Management Process Groups required for any project. These five process Groups have clear dependencies and are performed in the same sequence on each project.


The five Process Groups are :


Initiating  Process Group - Defines and authorizes the project or a project phase


Planning Process Group - Defines and refines objectives, and plans the course of action required to attain the objectives and scope that the project was undertaken to address.


Executing Process Group - Integrates people and other resources to carry out the project management plan for the project


Monitoring and Controlling process Group - Regularly measures and monitors progress to identify variances from the project management plan so that corrective action can be taken when necessary to meet project objectives.


Closing Process Group - Formalizes acceptance of the product, service or result and brings the project or a project phase to an orderly end.

Report Error

View answer Workspace Report Error Discuss

0 1897
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Development?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Project schedule network diagrams

  • Activity resource requirements

  • Resource calendars

  • Activity duration estimates 

  • Project management plan


                - RisK register


II. Tools and Techniques



  • Schedule network analysis

  • Critical path method

  • Schedule compression

  • What-if scenario analysis

  • Resource leveling

  • Critical chain method

  • Project management software

  • Applying calendars

  • Adjusting leads and lags 

  • Schedule model


III. Outputs



  • Project schedule

  • Schedule model data

  • Schedule baseline

  • Resource requirements (updates)

  • Activity attributes (updates)

  • Project calendar (updates)

  • Requested changes

  • Project management plan (updates)


                 - Schedule management plan(updates)

Report Error

View answer Workspace Report Error Discuss

0 1889
Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Information Distribution?

Answer

I. Inputs



  • Communications management plan


II. Tools and Techniques



  • Communications skills 

  • Information gathering and retrieval systems

  • Information distribution methods

  • Lessons learned process


III. Outputs



  • Organizational process assets (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 1880
Q:

4 phases of project management are

Answer

The project management life cycle describes high-level processes for delivering a successful project.


The project management life cycle is usually broken down into four phases:


1. Initiation and Planning,


2. Execution,


3. Project Monitoring and Control, and


4. Project Closing.

Report Error

View answer Workspace Report Error Discuss

6 1877
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Control ?

Answer

I. Inputs



  • Schedule management plan

  • Schedule baseline

  • Performance reports

  • Approved change requests


II. Tools and Techniques



  • Progress reporting

  • Schedule change control system

  • Performance measurement

  • Project management software

  • Variance analysis

  • Schedule comparision bar charts


III. Outputs



  • Schedule model data (updates)

  • Schedule baseline (updates)

  • Performance measurements

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Activity list (updates)

  • Activity attributes (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1858
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Qualitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement 

  • Risk management plan

  • Risk register


II.  Tools and Techniques



  • Risk probability and impact assesment

  • Probability and impact matrix

  • Risk data quality assessment

  • Risk categorization 

  • Risk Urgency assessment


III. Outputs



  • Risk register (updates)

Report Error

View answer Workspace Report Error Discuss

0 1855
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Perform Quality Control?

Answer

I. Inputs



  • Quality management plan

  • Quality metrics 

  • Quality checklists

  • Organizational process assets

  • Work performance information

  • Approved change requests

  • Deliverables


II. Tools and Techniques



  • Cause and effect diagram

  • Control charts

  • Flow Charting

  • Histogram

  • Pareto chart

  • Run chart

  • Scatter diagram

  • Statistical sampling

  • Inspection

  • Defect repair review


III. Outputs



  • Quality control measurements

  • Validated defect repair

  • Quality baseline (updates)

  • Recommended corrective actions

  • Recommended preventive actions

  • Requested changes

  • Recommended defect repair

  • Organization process assets (updates)

  • Validated deliverables

  • Project management plan (updates)


 


 

Report Error

View answer Workspace Report Error Discuss

0 1854