PMP Certification Questions

Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop Project Charter phase?

Answer

I. Inputs



  • Contract (when applicable)

  • Project statement of work

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project selection methods

  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs


         1. Project charter

Report Error

View answer Workspace Report Error Discuss

0 1853
Q:

Project Life Cycle

What is the Project Life Cycle?

Answer

Project managers or the organization can divide projects into phases to provide better management control with appropriate links to the ongoing operations of the performing organization. Collectively, these phases are known as the project life cycle.

Report Error

View answer Workspace Report Error Discuss

0 1853
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Quantitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Risk management plan

  • Risk register

  • Project management plan


                 - Project schedule management plan


                 - Project cost management plan


II. Tools and Techniques



  • Data gathering and representation techniques

  • Quantitative risk analysis and modeling techniques


III. Outputs



  • Risk register (updates)

Report Error

View answer Workspace Report Error Discuss

0 1844
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Resource Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Activity list

  • Activity attributes

  • Resource availability

  • Project management plan


II. Tools and Techniques



  • Expert Judgment

  • Alternatives analysis

  • Published estimating data

  • Project management software

  • Bottom-up estimating


III. Outputs



  • Activity resource requirements

  • Activity atributes (updates)

  • Resource breakdown structure

  • Resource calendars (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 1837
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Human Resource Planning?

Answer

I. Inputs



  • Enterprise Environmental factors

  • Organizational process assets

  • Project management plan


                  - Activity resource requirements


II. Tools and Techniques



  • Organization charts and position descriptions 

  • Networking

  • Organizational theory


III. Outputs



  • Roles and responsibilities

  • Project organization charts

  • Staffing management plan

Report Error

View answer Workspace Report Error Discuss

0 1830
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope control ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project scope management plan

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Change control system

  • Variance analysis

  • Replanning

  • Configuration management system


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure(updates)

  • WBS dictionary (updates)

  • Scope baseline (updates)

  • Requested changes

  • Recommended  corrective action

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1829
Q:

Project Communications Management

What are the Project Management Processes included in the Project Communications Management?

Answer

Communications planning - Determining the information and communications needs of the project stakeholders.


Information Distribution - Making needed information available  to project stakeholders in a timely manner.


Performance Reporting - Collecting and distributing performance information. This includes status reporting, progress measurement, and forecasting.


Manage Stakeholders - Managing communications to satisfy the requirements of and resolve issues with project stakeholders.

Report Error

View answer Workspace Report Error Discuss

0 1827
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Perform Quality Assurance?

Answer

I. Inputs



  • Quality management plan

  • Quality metrics

  • Process improvement plan 

  • Work performance information 

  • Approved change requests

  • Quality control measurements 

  • Implemented change requests

  • Implemented corrective actions 

  • Implemented defect repair

  • Implemented preventive actions 


II. Tools and Techniques



  • Quality planning tools and techniques

  • Quality audits

  • Process analysis 

  • Quality control tools and techniques


III. Outputs



  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1825