Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Risk Identification?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Risk management plan

  • Project management plan


II. Tools and Techniques



  • Documentation reviews

  • Information gathering techniques

  • Checklist analysis

  • Assumptions analysis

  • Diagramming techniques


III. Outputs



  • Risk register

Report Error

View answer Workspace Report Error Discuss

0 1768
Q:

You are planning to install and configure network services for ineroperability on your Windows 2000 Server computer. You specifically want this server to maintain and advertise a list of services that use the NWLink IPX/SPX/NetBIOS Compatible Transport Protocol. What service should you install?

A) Indexing Service B) NNTP Service
C) RIP Listener D) SAP Agent
 
Answer & Explanation Answer: D) SAP Agent

Explanation:

The SAP Agent enables a Windows 2000 computer to maintain and advertise a list of servers (such as NetWare servers) that use the NWLink IPX/SPX/NetBIOS Compatible Transport Protocol.

Report Error

View Answer Report Error Discuss

0 1753
Q:

Which of the following are displayed in File Explorer ?

A) Only OneDrive B) Only Storage locations
C) Both A & B D) Hardware devices such as monitors, printers, and cameras
 
Answer & Explanation Answer: C) Both A & B

Explanation:

Storage locations and OneDrive are both displayed in File Explorer.

Report Error

View Answer Report Error Discuss

9 1752
Q:

Which process ensures that the components of the computer are connected properly ?

A) Booting B) Saving
C) Processing D) Editing
 
Answer & Explanation Answer: A) Booting

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: CCENT
Job Role: Analyst

9 1750
Q:

What are Aggregates?

A. Subset of an InfoCube.

B. Outset of a Cube.

C. None of the above.

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP BW

0 1748
Q:

Customer Management, Order Management and Materials Management are all functions of which SAP Mobile Solution?

A. SAP Mobile Sales

B. SAP Mobile Service

C. SAP Mobile Procurement

D. SAP Mobile Direct Store Delivery

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

0 1748
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope Planning ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project charter

  • Priliminary project scope statement


II. Tools and Techniques



  • Expert Judgment

  • Templates, forms, standards


III. Outputs



  • Project scope management plan

Report Error

View answer Workspace Report Error Discuss

0 1741
Q:

[CO-OM-CCA] Accounting can be divided into internal and external accounting. Which of the following areas are part of internal accounting?

A. Product Cost Controlling

B. Overhead Cost Controlling

C. Asset Management

D. Financial Accounting

Answer

Answer : A , B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

0 1741