Q:

Project Management Process Groups

What are the Project Management Process Groups?

Answer

This section identifies and describes the five Project Management Process Groups required for any project. These five process Groups have clear dependencies and are performed in the same sequence on each project.


The five Process Groups are :


Initiating  Process Group - Defines and authorizes the project or a project phase


Planning Process Group - Defines and refines objectives, and plans the course of action required to attain the objectives and scope that the project was undertaken to address.


Executing Process Group - Integrates people and other resources to carry out the project management plan for the project


Monitoring and Controlling process Group - Regularly measures and monitors progress to identify variances from the project management plan so that corrective action can be taken when necessary to meet project objectives.


Closing Process Group - Formalizes acceptance of the product, service or result and brings the project or a project phase to an orderly end.

Report Error

View answer Workspace Report Error Discuss

0 2111
Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Budgeting ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Activity cost estimates

  • Activity cost estimate supporting detail

  • Project schedule 

  • Resource calendars 

  • Contract

  • Cost management plan


II. Tools and Techniques



  • Cost aggregation

  • Reserve analysis

  • Parametric estimating 

  • Funding limit reconciliation


III. Outputs



  • Cost baseline 

  • Project funding requirements 

  • Cost management plan (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2107
Q:

Project Human Resource Management

What are the Project Management Processes included in the Project Human Resource Management?

Answer

Human Resource Planning - Identifying and documenting Project roles, responsibilities, and reporting relationships, as well as creating the staffing management plan.


Acquire Project Team - Obtaining the human resources needed to complete the project


Develop Project Team - Improving the competencies and interaction of team members to enhance project performance.


Manage Project Team - Tracking team member performance, providing feedback, resolving issues, and coordinating changes to enhance project performance.

Report Error

View answer Workspace Report Error Discuss

0 2099
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Resource Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Activity list

  • Activity attributes

  • Resource availability

  • Project management plan


II. Tools and Techniques



  • Expert Judgment

  • Alternatives analysis

  • Published estimating data

  • Project management software

  • Bottom-up estimating


III. Outputs



  • Activity resource requirements

  • Activity atributes (updates)

  • Resource breakdown structure

  • Resource calendars (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2098
Q:

Before you can create cost centers, you must first create a _______ heirarchy.

A. Logical

B. Optimum

C. Complete

D. Standard

Answer

Answer : D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

0 2098
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop project management plan phase?

Answer

I. Inputs



  • Preliminary project scope statement

  • Project management processes

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Project management plan

Report Error

View answer Workspace Report Error Discuss

0 2094
Q:

You are creating an ASP.NET application for XYZ. The company data is stored in a Microsoft SQL Server 6.5 database. Your application generates accounting summary reports based on transaction tables that contain million of rows.


You want your application to return each summary report as quickly as possible. You need to configure your application to connect to the database and retrieve the data in a away that achieves this goal.


What should you do?

A) Use a SqlConnection object to connect to the database, and use a SqlCommand object to run a stored procedure that returns the data. B) Use an OleDbConnection object to connect to the database, and use an OleDbCommand object to run a stored procedure that returns the data.
C) Configure SQL Server to support HTTP access, and create an XML template to run a stored procedure that returns the data in XML format. D) Use COM interop to create an ADODB.Connection object, and use an ADODB.Command object to run a SQL statement that returns the data.
 
Answer & Explanation Answer: B) Use an OleDbConnection object to connect to the database, and use an OleDbCommand object to run a stored procedure that returns the data.

Explanation:

We need to use an OleDBConnection to connect to SQL Server Version 6.5 (or earlier). 

 

Incorrect Answers:

 

A: We could use a SqlConnection object only if the SQL Server were SQL Server 7.0, 2000 or later.

 

C: HTTP functionality is not required in this scenario. It would introduce unnecessary overhead.

 

D: ADODB is a legacy standard and should not be used here

Report Error

View Answer Report Error Discuss

1 2093
Q:

For employees who do not use time recording, actual times for processing type M can also be recorded using the ... infotype.

A. Interval

B. Wage

C. Identity

D. Overtime

Answer

Answer : D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP HR

0 2092