Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Perform Quality Assurance?

Answer

I. Inputs



  • Quality management plan

  • Quality metrics

  • Process improvement plan 

  • Work performance information 

  • Approved change requests

  • Quality control measurements 

  • Implemented change requests

  • Implemented corrective actions 

  • Implemented defect repair

  • Implemented preventive actions 


II. Tools and Techniques



  • Quality planning tools and techniques

  • Quality audits

  • Process analysis 

  • Quality control tools and techniques


III. Outputs



  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2156
Q:

For employees who do not use time recording, actual times for processing type M can also be recorded using the ... infotype.

A. Interval

B. Wage

C. Identity

D. Overtime

Answer

Answer : D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP HR

0 2150
Q:

You create an ASP.NET page that uses images to identify areas where a user can click to initiate actions. The users of the application use Internet Explorer.


You want to provide a pop-up window when the user moves the mouse pointer over an image. You want the pop-up window to display text that identifies the action that will be taken if the user clicks the image.


What should you do?

A) For each image, set the AlternateText property to specify the text you want to display, and set the ToolTip property to True. B) For each image, set the ToolTip property to specify the text you want to display.
C) In the onmouseover event handler for each image, add code that calls the RaiseBubbleEvent() method of the System.Web.UI.WebControls.Image class. D) In the onmouseover event handler for each image, add code that calls the ToString() method of the System.Web.UI.WebControls.Image class.
 
Answer & Explanation Answer: B) For each image, set the ToolTip property to specify the text you want to display.

Explanation:

WebControl.ToolTip property gets or sets the text displayed when the mouse pointer hovers over the Web server control. The use of the ToolTip property meets the requirement of this scenario.

 

Incorrect Answers:

A: The AlternateText property is used to specify the text to display if the image is not available.


C: The RaiseBubbleEvent is not useful here. ASP.NET server controls such as the Repeater, DataList and DataGrid Web controls can contain child controls that raise events. Rather than each button raising an event individually, events from the nested controls are "bubbled"—that is, they are sent to the control's parent.


D: The ToStringMethod() would not by itself provide the functionality required.

Report Error

View Answer Report Error Discuss

0 2148
Q:

Project Management Process Groups

What are the Project Management Process Groups?

Answer

This section identifies and describes the five Project Management Process Groups required for any project. These five process Groups have clear dependencies and are performed in the same sequence on each project.


The five Process Groups are :


Initiating  Process Group - Defines and authorizes the project or a project phase


Planning Process Group - Defines and refines objectives, and plans the course of action required to attain the objectives and scope that the project was undertaken to address.


Executing Process Group - Integrates people and other resources to carry out the project management plan for the project


Monitoring and Controlling process Group - Regularly measures and monitors progress to identify variances from the project management plan so that corrective action can be taken when necessary to meet project objectives.


Closing Process Group - Formalizes acceptance of the product, service or result and brings the project or a project phase to an orderly end.

Report Error

View answer Workspace Report Error Discuss

0 2147
Q:

You want to move the Philadelphia OU from the acme1.com domain to the acme2.com domain. Which tool should you use?

A) MoveTree.exe B) The move command -line utility
C) Server Extensions Administrator D) Active Directory Domains and Trusts
 
Answer & Explanation Answer: A) MoveTree.exe

Explanation:

Use MoveTree.exe to move Active Directory objects from one domain to another.

Report Error

View Answer Report Error Discuss

0 2146
Q:

A manager in your office received a new Windows 2000 Professional laptop computer. You have been asked to configure offline files for the manager to work on documents at home. You enable offline files, and have the manager log off of the network. During the logoff process, the expected synchronization of offline files does not occur. You have the manager log back on to the network. What can you do to correct the problem?

A) Enable file and print sharing. When the manager logs off, the files will synchronize. B) Manually synchronize all offline files.
C) On the server, make all files available offline. When the manager logs off, the files will synchronize. D) Do nothing. Windows 2000 Professional does not tell you when Synchronization happens.
 
Answer & Explanation Answer: C) On the server, make all files available offline. When the manager logs off, the files will synchronize.

Explanation:
Report Error

View Answer Report Error Discuss

0 2146
Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Budgeting ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Activity cost estimates

  • Activity cost estimate supporting detail

  • Project schedule 

  • Resource calendars 

  • Contract

  • Cost management plan


II. Tools and Techniques



  • Cost aggregation

  • Reserve analysis

  • Parametric estimating 

  • Funding limit reconciliation


III. Outputs



  • Cost baseline 

  • Project funding requirements 

  • Cost management plan (updates)

  • Requested changes

Report Error