Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Quality Planning ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Project management plan


II. Tools and Techniques



  • Cost - benifit analysis

  • Benchmarking

  • Design of experiments

  • Cost of quality(COQ)

  • Additional quality planning tools


III. Outputs



  • Quality management plan

  • Quality metrics 

  • Quality checklists

  • Process improvement plan

  • Quality baseline

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1914
Q:

Executing Process Group

What are the Project Management Processes included in the Executing Process Group?

Answer


    • Direct and Manage Project Execution

    • Perform Quality Assurance

    • Acquire Project Team

    • Develop Project Team

    • Information Distribution

    • Request Seller Responses

    • Select Sellers


Report Error

View answer Workspace Report Error Discuss

0 1914
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Manage Project Team?

Answer

I. Inputs



  • Organizational process assets

  • Project staff assignments

  • Roles and responsibilities

  • Project organization charts

  • Staffing management plan

  • Team performance assessment

  • Work performance information

  • Performance reports


II. Tools and Techniques



  • Observation and conversation

  • project performance appraisals

  • Conflict management

  • Issue log


III. Outputs



  • Requested changes

  • Recommended corrective actions

  • Recommended preventive actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1912
Q:

Word 2010 has a particular template that it uses when you first open the program. This template contains default styles, no text and you also use it when you create new, blank documents. As you customize styles, marcos and other elements these settings are automatically stored in this template.

 

What is the name of this template file?

A) Standard.dotx B) Normal.dotx
C) Empty.dotx D) Template.dotx
 
Answer & Explanation Answer: B) Normal.dotx

Explanation:
Report Error

View Answer Report Error Discuss

1 1911
Q:

You want to configure a static IP address on a Windows 2000 Server  computer on which you want to install the DNS Server service and Active Directory. What tool should you use to configure the static IP address?

A) IPconfig.exe B) DNS administrative tool
C) Active Directory Users and Computers D) Network and Dial-up connections folder
 
Answer & Explanation Answer: D) Network and Dial-up connections folder

Explanation:

A static IP address is specified by configuring the Local Area Connection in the Network and Dial - up Connections folder.

Report Error

View Answer Report Error Discuss

0 1910
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Develop Project Team?

Answer

I. Inputs



  • Project staff assignments

  • Staffing management plan

  • Resource availability


II. Tools and Techniques



  • General management skills

  • Training

  • Team - building activities

  • Ground rules

  • Co-location

  • Recognition and rewards


III. outputs



  • Team performance assessment

Report Error

View answer Workspace Report Error Discuss

0 1908
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Risk Response Planning?

Answer

I. Inputs



  • Risk management plan

  • Risk register


II. Tools and Techniques



  • Strategies for negative risk or threats

  • Strategies for positive risks or opportunities

  • Strategies for both threats and opportunities

  • Contingent response strategy


III. Outputs



  • Risk register (updates)

  • Project management plan (updates)

  • Risk - related contractual agreements

Report Error

View answer Workspace Report Error Discuss

0 1903
Q:

Which Windows 2000 tool can you use to initiate the transfer of images from a digital camera to your Windows 2000 computer?

A) Imaging B) Wireless Link
C) Scanners and Cameras D) Sounds and Multimedia
 
Answer & Explanation Answer: A) Imaging

Explanation:

The Imaging application (Start => Programs => Accessories => Imaging) is the only windows 2000 application that can be used to initiate image transfer. You can use Wireless Link to configure how Windows 2000 will handle received image files, but you can't use Wireless Link to initiate the image transfer.

Report Error

View Answer Report Error Discuss

0 1900