Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Request Seller Responses?

Answer

I. Inputs



  • Organizational process assets

  • Procurement management plan

  • Procurement documents


II. Tools and Techniques



  • Bidder conferences

  • Advertising

  • Develop qualified sellers list


III. Outputs



  • Qualified sellers list

  • Procurement document package

  • Proposals

Report Error

View answer Workspace Report Error Discuss

0 2027
Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Information Distribution?

Answer

I. Inputs



  • Communications management plan


II. Tools and Techniques



  • Communications skills 

  • Information gathering and retrieval systems

  • Information distribution methods

  • Lessons learned process


III. Outputs



  • Organizational process assets (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2027
Q:

You are the database administrator of a SQL Server 2000 computer. The server contains your company's Accounts database. Hundreds of users access the database each day.Because you have had power interruptions in the past, you want to protect the physical integrity of the Accounts database. You do not want to slow down server operations.What should you do?

A) Create a database maintenance plan to check database integrity and make repairs each night. B) Enable the torn page detection database option for each database.
C) Disablewrite caching on all disk controllers. D) Ensure that write caching disk controllers have battery backups.
 
Answer & Explanation Answer: D) Ensure that write caching disk controllers have battery backups.

Explanation:

The scenario states that power interruptions have occurred in the past. By buying a battery backup solution for the disk controllers the power interruption problem would be prevented.

Report Error

View Answer Report Error Discuss

0 2023
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Manage Project Team?

Answer

I. Inputs



  • Organizational process assets

  • Project staff assignments

  • Roles and responsibilities

  • Project organization charts

  • Staffing management plan

  • Team performance assessment

  • Work performance information

  • Performance reports


II. Tools and Techniques



  • Observation and conversation

  • project performance appraisals

  • Conflict management

  • Issue log


III. Outputs



  • Requested changes

  • Recommended corrective actions

  • Recommended preventive actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2020
Q:

What function are available during packing?

A. Proposing allowed handling units.

B. Performing multi-level packing.

C. Automatically dividing the delivery items among handling units.

D. Packing or unpacking handling units.

Answer

Answer : A , B , C, ,D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP SD

0 2019
Q:

You are experiences problems when starting Word 2010. The software just keeps on crashing and never fully loads. Your colleague has recommended that you start Word in a particular mode. What could this be?

A) Safe Mode B) Private Mode
C) Easy Mode D) Invulnerable mode
 
Answer & Explanation Answer: A) Safe Mode

Explanation:
Report Error

View Answer Report Error Discuss

2 2018
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Develop Project Team?

Answer

I. Inputs



  • Project staff assignments

  • Staffing management plan

  • Resource availability


II. Tools and Techniques



  • General management skills

  • Training

  • Team - building activities

  • Ground rules

  • Co-location

  • Recognition and rewards


III. outputs



  • Team performance assessment

Report Error

View answer Workspace Report Error Discuss

0 2014
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Acquire Project Team?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Roles and responsibilities 

  • Project organization charts

  • Staffing management plan


II. Tools and Techniques



  • Pre-assignment

  • Negotiation

  • Acquisition

  • Virtual teams


III. Outputs



  • Project staff assignments

  • Resource availability

  • Staffing management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2014