Certification Questions

Q:

When is redistribution required for EIGRP?

Answer

Redistribution is required when more than one EIGRP session or process is running and they are identified with different ASNs. Redistribution shares topology information between EIGRP sessions.

Report Error

View answer Workspace Report Error Discuss

Subject: CCNA

0 2148
Q:

Project Cost Management

What are the Project Management Processes included in the Project Cost Management?

Answer

Cost Estimating - Developing an approximation of the costs of the resources needed to complete  project activities.


Cost Budgeting - Aggregating the estimated costs of individual activities or work packages to establish a cost baseline


Cost Control - Influencing the factors that create cost variances and controlling changes to the project budget.

Report Error

View answer Workspace Report Error Discuss

0 2147
Q:

You are choosing a Windows 2000 operating system to use on a new computer at your company. This new computer will be a heavily used SQL server in your enterprise network environment. which operating system should you choose?

A) Windows 2000 professional B) Windows 2000 Server
C) Windows 2000 Advanced Server D) Windows 2000 Datacenter Server
 
Answer & Explanation Answer: C) Windows 2000 Advanced Server

Explanation:

Windows 2000 Advanced Server is optimized for use on servers (such as SQL servers) in an enterprise network environment.

Report Error

View Answer Report Error Discuss

0 2146
Q:

Planning Process Group

What are the Project Management Processes included in the Planning Process Group?

Answer



      • Develop Project Management Plan

      • Scope Planning

      • Scope Definition

      • Create WBS

      • Activity Definition

      • Activity Sequencing

      • Activity Resource Estimating

      • Activity Duration Estimating

      • Schedule Development

      • Cost Estimating

      • Cost Budgeting

      • Quality Planning

      • Human Resource Planning

      • Communications Planning

      • Risk Management Planning

      • Risk Identification

      • Qualitative Risk Analysis

      • Quantitative Risk Analysis

      • Risk Response Planning

      • Plan purchases and Acquisitions

      • Plan Contracting



Report Error

View answer Workspace Report Error Discuss

0 2145
Q:

Clossing Process Group

What are the Project Management Processes included in Closing Process Group?

Answer


    • Close Project

    • Contract Closure



 

Report Error

View answer Workspace Report Error Discuss

0 2144
Q:

The president of your company collects manager's weekly reports in a shared folder on her Windows 2000 Professional computer called reports. Because the reports contain sensitive information, she asks you to prevent users from enabling offline access for the network share that contains the financial report. What should you do?

A) Use Windows Explorer to disable Offline Files. B) Use Windows Explorer to disable Caching for the reports on the network share.
C) Set the Manager's access level to read-only. D) Implement a domain policy to block the synchronization of offline files.
 
Answer & Explanation Answer: B) Use Windows Explorer to disable Caching for the reports on the network share.

Explanation:
Report Error

View Answer Report Error Discuss

0 2140
Q:

At which point can goods issue be posted if qualitiy inspection is configured with Sales&Distribuiton?

A. Upon acceptance of the inspection lot.

B. Upon completing the delivery.

C. Upon creating the transfer order.

D. Upon confirming the picking quantities.

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP SD

0 2139
Q:

Project Procurement Management

What are the Project Management Processes included in the Project Procurement Management?

Answer

The Project Procurement Management processes include the following:


Plan Purchases and Acquisitions - determining what to purchase or acquire and determining when and how.


Plan Contracting - documenting products, services, and results requirements and identifying potential sellers.


Request Seller Responses - obtaining information, quotations, bids, offers, or proposals, as appropriate.


Select Sellers - reviewing offers, choosing among potential sellers, and negotiating a written contract with each seller.


Contract Administration - managing the contract and relationship between the buyer and seller , reviewing and documenting how a seller is performing or has performed to establish required corrective actions and provide a basis for future relationships with the seller, managing contract-related changes and, when appropriate , managing the contractual relationship with the outside  buyer of the project.


Contract Closure - completing and settling each contract, including the resolution of any open items, and closing each contract applicable to the project or a project phase 

Report Error

View answer Workspace Report Error Discuss

0 2136