Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 4863
Q:

A resolution declaring Purna Swaraj (complete independence) as Indian's political goal was passed in the ..........Congress of 1929

A) Simla B) Lahore
C) Madras D) Calcutta
 
Answer & Explanation Answer: B) Lahore

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History

2 4862
Q:

Hitendra Desai was known outstanding in which field ?

A) Literature B) Politics
C) Journalism D) Social Service
 
Answer & Explanation Answer: B) Politics

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Famous Personalities

4 4861
Q:

Thomas cup is associated with which game?

A) Football B) Cricket
C) Badminton D) Chess
 
Answer & Explanation Answer: C) Badminton

Explanation:

Thomas cup is associated with Badminton. It is a competition among teams representing member nations of the Badminton World Federation (BWF).

Thomas_trophy_is_associated_with1557898491.jpg image

Report Error

View Answer Report Error Discuss

Filed Under: Sports
Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

6 4860
Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4859
Q:

Select the word with the correct spelling.

 

A) oxidieser B) thespian
C) aproval D) secreetes
 
Answer & Explanation Answer: B) thespian

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 4858
Q:

The schools which taught primary education to Muslims during the period of sultanate

A) Mukhaddams B) Makthabs
C) Kohies D) None
 
Answer & Explanation Answer: B) Makthabs

Explanation:

Makthabs taught the primary education to muslims during the period of sultanate

Report Error

View Answer Report Error Discuss

Filed Under: World History

6 4857
Q:

Which best describes genetic mutations?

A) Genetic mutations that cause diseases are always passed on to offspring. B) Some inherited genetic mutations can be good for the offspring.
C) Different genetic mutations cause few forms of cancer. D) Somatic mutations can be inherited from parents or acquired during life.
 
Answer & Explanation Answer: B) Some inherited genetic mutations can be good for the offspring.

Explanation:

Mutations are accidents in the copying of DNA. A genetic mutation is a random change in the DNA that is passed on further generations of cells and or organisms. 

 

Genetic mutations are accidental changes in the DNA in the germ cells or early in the formation of the embryo. These changes if they are in the germ cell will be passed on to other organisms formed by sexual reproduction or asexual reproduction. An example would be the golden delicious apple. A lost of genetic information due to a mutation resulted in a different color of fruit.

 

Genetic mutations that cause diseases are not always passed on to offspring. 

Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

3 4848