Questions

Q:

Rearrange the parts of the sentence in correct order.

It secured support from

P-government, a significant development in itself
Q-other sections of the
R-Opposition, and defeated the

 

A) RQP B) QRP
C) PRQ D) PQR
 
Answer & Explanation Answer: B) QRP

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 10650
Q:

Arrange the following cities in an order from North to South

1) Bhubaneshwar
2) Chennai
3) Hyderabad
4) Cochin

A) 1 3 2 4 B) 1 2 3 4
C) 1 2 4 3 D) 1 3 4 2
 
Answer & Explanation Answer: A) 1 3 2 4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Geography
Exam Prep: Bank Exams

1 10642
Q:

_________ hard drives are permanently located inside the system unit and are not designed to be removed, unless they need to be repaired or replaced

A) Static B) Internal
C) External D) Remove
 
Answer & Explanation Answer: B) Internal

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Computer
Exam Prep: Bank Exams
Job Role: Bank Clerk

18 10638
Q:

An area of dead myocardial tissue is called

A) an infarct B) stenosis
C) an induration D) hypertrophy
 
Answer & Explanation Answer: A) an infarct

Explanation:

An area of dead myocardial tissue is called an infarct.

Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE
Job Role: Analyst , Bank Clerk

18 10636
Q:

Why are CPM, GERT, and PERT not considered sufficient to create a project schedule?

A) All three are tools and techniques of schedule development, not the actual schedule B) As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations
C) They are sufficient. Each calculates early and late start and finish dates for each activity D) They are Monte Carlo techniques used to provide what-if analysis for adverse external factors on a project
 
Answer & Explanation Answer: B) As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations

Explanation:

Answer A is tempting because it is true by definition, but Answer B is correct because it properly answers the question, in that these techniques do not take into account resource pool constraints. Answer C is incorrect because it provides possible early and late start and finish dates, but not the actual schedules. Answer D is incorrect because none of the the three are simulation techniques. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 10635
Q:

Select the antonym of

 

escort

 

A) entourage B) cavalier
C) foe D) convoy
 
Answer & Explanation Answer: C) foe

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 10631
Q:

Rearrange the parts of the sentence in correct order

 

By doing so, it

P-­brought it closer
Q­-to cultural and social life
R­-has redefined politics and

 

A) RPQ B) RQP
C) PQR D) QPR
 
Answer & Explanation Answer: A) RPQ

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 10631
Q:

What value should come in place of the question mark (?) in the following question?

264÷576+112+12 = ?2

A) 44 B) 12
C) 15 D) 14
 
Answer & Explanation Answer: B) 12

Explanation:
264 / 24 + 121 + 12 = (?)^2 11 + 121 + 12 = (?)^2 144 = (?)^2 (?) = 12
Report Error

View Answer Report Error Discuss

0 10627