Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

X can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?

A) 40/9 B) 9/40
C) 44/9 D) 9/44
 
Answer & Explanation Answer: A) 40/9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1323
Q:

A and B together do a job in 12 days and A could do the job in 20 days if he worked alone. How many days would B take to do the job if he worked alone?

A) 30 B) 25
C) 24 D) 15
 
Answer & Explanation Answer: A) 30

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1320
Q:

A school has 8 periods of 45 minutes each, every day. How long will each period be if the school has to have 9 periods everyday, assuming the working hours to be the same?

A) 40 min B) 35 min
C) 30 min D) 45 min
 
Answer & Explanation Answer: A) 40 min

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1318
Q:

If two flood gates A and B function simultaneously, the reservoir will be filled iu 6 hours. Gate A fills the reservoir 5 hours faster than gate B. How many hours does the faster flood gate take to fill the reservoir?

A) 7 hrs B) 13 hrs
C) 5 hrs D) 10 hrs
 
Answer & Explanation Answer: D) 10 hrs

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT

2 1317
Q:

10 people can build a wall in 12 days. Six people, each only half as efficient as those in the first group, will be able to complete 3/5 of such a wall in

A) 24 days B) 20 days
C) 18 days D) 25 days
 
Answer & Explanation Answer: A) 24 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1313
Q:

P, Q and R together can make a table in 40 minutes. P and Q together can make it in 60 minutes. How much time (in minutes) will R alone take to make the table?

A) 100 B) 120
C) 90 D) 150
 
Answer & Explanation Answer: B) 120

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1312
Q:

Raja and Kundan together can build a wall in 20 days, Kundan and Mahesh build the same wall in 30 days and Mahesh and Raja can build the same wall in 24 days. In how many days can all the three complete the same wall while working together?

A) 18 B) 16
C) 20 D) 14
 
Answer & Explanation Answer: B) 16

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1310
Q:

Pankaj has done 1/2 of a job in 12 days, Sainath completes the rest of the job in 6 days. In how many days can they together do the job?

A) 4 days B) 12 days
C) 8 days D) 16 days
 
Answer & Explanation Answer: C) 8 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1306