Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

24 men can repair a road in 50 days. If they are joined by 16 more men, then in how much time (in days) the road can be repaired?

A) 28 B)  25
C) 32 D) 30
 
Answer & Explanation Answer: D) 30

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1479
Q:

Ajay can do a painting in 12 days. Amit is 70% more efficient than Ajay. What is the number of days Amit would need to finish the same painting?

 

A) 6415 B) 5113
C) 335 D) 7117
 
Answer & Explanation Answer: D) 7117

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1470
Q:

P and Q can do a project in 12 and 12 days respectively. In how many days can they complete 50% of the project if they work together?

A) 6 days B) 3 days
C) 18 days D) 1.5 days
 
Answer & Explanation Answer: B) 3 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1463
Q:

A painter can paint a fence in 24 hours. After 6 hours he takes a break. What fraction of the fence is yet to be painted?

A) 0.6 B) 0.2
C) 0.75 D) 0.8
 
Answer & Explanation Answer: C) 0.75

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1458
Q:

Pramod can paint a wall red in 12 hours while Brajen can whitewash the wall completely in 16 hrs. If Pramod and Brajen work alternately for an hour each starting when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?

 

A) 89 B) 96
C) 48 D) 95
 
Answer & Explanation Answer: A) 89

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1450
Q:

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is

A) 20 days B) 21 days
C) 22 days D) 24 days
 
Answer & Explanation Answer: D) 24 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1446
Q:

Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?

A) 3/5 B) 1/3
C) 1/2 D) 2/5
 
Answer & Explanation Answer: D) 2/5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 1445
Q:

Ram and Shyam undertook a work for Rs 5600. Ram alone can do the work in 5 days and Shyam alone can do the work in 9 days. If they worktogether, then what will be the difference (in Rs.) in the amount they receive?

A) 1800 B) 2400
C) 1600 D) 2200
 
Answer & Explanation Answer: C) 1600

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

6 1436