Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A and B together can do a piece of work in 9 days. If A does thrice the work of B in a given time, the time A alone will take to finish the work is

A) 4 days B) 6 days
C) 8 days D) 12 days
 
Answer & Explanation Answer: D) 12 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

6 2028
Q:

P and Q can do a project in 6 and 12 days respectively. In how many days can they complete 25% of the project if they work together?

A) 2 days B) 4 days
C) 1 days D) 8 days
 
Answer & Explanation Answer: C) 1 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 2009
Q:

A labourer can do a job in 50 hours. After 5 hours he takes a break. What fraction of the job is yet to be done?

A) 0.8 B) 0.5
C) 0.75 D) 0.9
 
Answer & Explanation Answer: D) 0.9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 2002
Q:

S, T and U together can complete a work in 30 days. If the ratio of efficiency of S, T and U is 20 : 15 : 12 respectively, then in how many days U alone can complete the same work?

A) 195/2 B) 235/2
C) 225/2 D) 215/2
 
Answer & Explanation Answer: B) 235/2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

7 1968
Q:

Prabhat has done 1/2 of a job in 12 days. Santosh completes the rest of the job in 6 days. In how many days can they together do the job?

A) 12 days B) 4 days
C) 8 days D) 16 days
 
Answer & Explanation Answer: C) 8 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE

2 1943
Q:

P and Q can do a project in 150 and 100 days respectively. In how many days can they complete 60% of the project if they work together?

A) 12 days B) 72 days
C) 42 days D) 36 days
 
Answer & Explanation Answer: D) 36 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1937
Q:

A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in

A) 8 days B) 7.5 days
C) 6.4 days D) 5.5 days
 
Answer & Explanation Answer: B) 7.5 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1935
Q:

50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

A) 36 B) 38
C) 40 D) 45
 
Answer & Explanation Answer: C) 40

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , Bank Exams
Job Role: Bank PO , Bank Clerk

3 1914