FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Amit can do a piece of work in 45 days, but Bharath can do the same work in 5 days less, than Amit, when  working alone. Amit and Bharath both started the work together but Bharath  left after some days and Amit finished the remaining work in 56 days with half of his efficiency but he did the work with Bharath with his complete efficiency. For how many days they had worked together?

A) 6 B) 8
C) 9 D) 12
 
Answer & Explanation Answer: B) 8

Explanation:

    AmitBharatNo.of Days4540Efficiency2.22Percent(=145)2.5 Percent(=140)

 

Amit did the work in 56 days = 56×145×2=2845 

 

Therefore, Rest work 17/45 was done by Amit and Bharath = 174517360 = 8 days

 

 

 

( since Amit and Bharath  do the work in one day = 145+140=17360)

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Bank Clerk , Bank PO

30 15580
Q:

Five men and nine women can do a piece of work in 10 days. Six men and twelve women can do the same work in 8 days. In how many days can three men and three women do the work  ?

A) 18 days B) 20 days
C) 16 days D) 14 days
 
Answer & Explanation Answer: B) 20 days

Explanation:

(5m + 9w)10 = (6m + 12w)8 

=> 50m + 90w = 48w + 96 w    => 1m = 3w

5m + 9w = 5m + 3m = 8m

 

8 men can do the work in 10 days.

3m +3w = 3m + 1w = 4m

So, 4 men can do the work in (10 x 8)/4 = 20 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

9 15275
Q:

A is 3 times faster than B. If A can finish a work 32 days less than that of B, find the number of days need to finish the work if both are working together?

A) 12 days B) 24 days
C) 32 days D) 16 days
 
Answer & Explanation Answer: A) 12 days

Explanation:

It is given that efficiency ratio =3:1

so time ratio will be 1:3 (since work is same)

 

Also given that time diff = 32 days. ratio difference = 3-1 =2 

2 ratio = 32 days

1 ratio = 16 days.

So A will alone finish it in 16 days and B will finish it in 16*3 = 48 days.

 

Total work = LCM of 16 and 48 = 48.

Total time = Total work/Total efficiency 

ie; 48/4= 12 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams
Job Role: Bank PO , Bank Clerk

8 15206
Q:

6 men can complete a piece of work in 12 days. 8 women can complete the same piece of work in 18 days whereas 18 children can complete the piece of work in 10 days. 4 men, 12 women and 20 children work together for 2 days. If only men were to complete the remaining work in 1 day how many men would be required totally?

A) 38 B) 72
C) 36 D) 76
 
Answer & Explanation Answer: C) 36

Explanation:

Given 4men, 12 women and 20 children work for  2 days.

Workdone for 2 days by 4men, 12 women and 20 children = 4 x 26 x 12 + 12 x 28 x 18 + 20 x 218 x 10 = 12

Therefore, remaining work = 1 - 12 = 12

To complete the same work by only men in 1 day,

We know that M1 x D1 = M2 x D2

Here M1 = 6 , D1 = 12 and M2 = M , D2 = 1

12 x 6 = M x 1

=> M = 12 x 6 = 72

=> But the remaining work = 1/2

Men required => 1/2 x 72 = 36

Only men required to Complete the remaining work in 1 day = 36.

 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

20 14082
Q:

Two pipes A and B can fill a cistern in 4 minutes and 6 minutes respectively . If these pipes are turned on alternately for 1 minute each how long will it take to the cistern to fill?

Answer

As the pipes are operating alternatively, thus their 2 minutes job is = 14 + 16 = 512 


In the next 2 minutes the pipes can fill another 512 part of cistern. 


Therefore, In 4 minutes the two pipes which are operating alternatively will fill 512 + 512 = 56Remaining part = 1 - 56 = 16 


Pipe A can fill 14 of the cistern in 1 minute 


Pipe A can fill 16 of the cistern in = 23 min 


Therefore, Total time taken to fill the Cistern  


4 + 23 minutes.

Report Error

View answer Workspace Report Error Discuss

Subject: Time and Work Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

28 13957
Q:

A garrison of 2000 men has provisions for 54 days. At the end of 15 days, a reinforcement arrives, and it is now found that the provisions will last only for 20 days more. What is the reinforcement ?

A) 1900 B) 2100
C) 1700 D) 2000
 
Answer & Explanation Answer: A) 1900

Explanation:

Given 2000 ---- 54 days

The provisions for 2000 men for 39 days can be completed by 'm' men for only 20 days.

i.e, 2000 ----- 39 days == m ---- 20 days

=> m x 20 = 2000 x 39

m = 3900

So total men for 20 days is 3900

=> 2000 old and 1900 new reinforcement.

Hence, reinforcement = 1900.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

10 13936
Q:

Kaushalya can do a work in 20 days, while kaikeyi can do the same work in 25 days. They started the work jointly.Few days later Sumitra also joined them and thus all of them completed the whole work in 10 days. All of them were paid total Rs.700. What is the Share of Sumitra?

A) Rs.130 B) Rs.185
C) Rs.70 D) can't be determined
 
Answer & Explanation Answer: C) Rs.70

Explanation:

Efficiency of kaushalya = 5%

Efficiency of kaikeyi  = 4%

Thus, in 10 days working together they will complete only 90% of the work.

          [(5+4)*10] =90

Hence, the remaining work will surely done by sumitra, which is 10%.

Thus, sumitra will get 10% of Rs. 700, which is Rs.70

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

12 13671
Q:

12 men complete a work in 9 days. After they have worked for 6 days, 4 more men join them. How many days will they take to complete the remaining work ?

A) 2 days B) 2.5 days
C) 2.25 days D) 3 days
 
Answer & Explanation Answer: C) 2.25 days

Explanation:

1 man's 1 day work = 1/108
12 men's 6 day's work = 1/9 x 6 = 2/3

Remaining work = 1 - 2/3 = 1/3

16 men's 1 day work = 1/108 x 16 = 4/27
4/27 work is done by them in 1 day.

1/3 work is done by them in 27/4 x 1/3 = 9/4 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

18 13649