Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

X, Y and Z can do a piece of work in 30, 40 and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

A) 660/47 B) 640/47
C) 680/47 D) 665/47
 
Answer & Explanation Answer: A) 660/47

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1273
Q:

A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in

A) 16 days B) 24 days
C) 28 days D) 29 days
 
Answer & Explanation Answer: B) 24 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1273
Q:

A canal of a village can be cleaned by 24 villagers in 12 days. The number of days in which 36 villagers can clean the canal is ?

A) 18 B) 8
C) 72 D) 16
 
Answer & Explanation Answer: B) 8

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1270
Q:

A mason can build a wall in 70 hours. After 7 hours he takes a break. What fraction of the wall is yet to be built?

A) 0.9 B) 0.8
C) 0.5 D) 0.75
 
Answer & Explanation Answer: A) 0.9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1262
Q:

Akhilesh is two times as good a workman as Bansi and therefore is able to finish a job in 39 days less than Bansi. Working together, they can do it in

A) 13 days B) 24 days
C) 26 days D) 12 days
 
Answer & Explanation Answer: C) 26 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams , CAT

1 1255
Q:

A work can be completed by 28 women in 36 days. If 4 women leave after working for 18 days, then how many days will be needed to complete the remaining work?

A) 24 B) 21
C) 27 D) 25
 
Answer & Explanation Answer: B) 21

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1254
Q:

Surya works 3 times as fast as Ramya and is able to complete a work in 40 days less than the number of days taken by Ramya. Find the time in which they can complete the work together.

A) 20 days B) 15 days
C) 25 days D) 30 days
 
Answer & Explanation Answer: B) 15 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1254
Q:

S and T can finish a work in 50 days. They worked together for 20 days and then left. How much of the work is left?

A) 3/5 B) 1/3
C) 1/2 D) 2/5
 
Answer & Explanation Answer: A) 3/5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1254