Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A takes 24 day in completing a work alone. Time taken by A in completing 1/3rd of the work is equal to the time taken by B in completing half of the work. How many days will be taken in completing the work if both A & B start working together?

A) 21/3 days B) 48 days
C) 40 days D) 48/5 days
 
Answer & Explanation Answer: D) 48/5 days

Explanation:

Ans. 
Time taken by A to complete a work alone - 24 days
Time taken by A in completing 1/3 of work = 24*1/3= 8 Days
8 day = time taken by B in completing 1/2 of work
B alone can complete the work = 16 days
The required time in completing the work if both A & B start working together?
16*24 / 40 = 48/5 Days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , GATE

2 2860
Q:

A,B and C together can finish a task in 7.5 days. C is thrice as productive as A and B alone can do the task in 15 days. In how many days can A and C do the job if B goes on leave?

A) 30 B) 10
C) 20 D) 15
 
Answer & Explanation Answer: D) 15

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

11 2795
Q:

A does 75% of a work in 25 days. He then calls in B and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?

A) 50 days B) 80 days
C) 24 days D) 37.5 days
 
Answer & Explanation Answer: A) 50 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 2772
Q:

Concept of Nehative Work

A tub can be filed in 20 minutes but there is a lekage in it which can empty the full tub in 60 minutes. In how many minutes it can be filled?

Answer

Filling efficiency = 5%        


Emptying efficiency = 1.66%  


Net efficiency = 5-1.66 = 3.33%


Therefore, Required time to fil the tub =100/3.33= 30 minutes

Report Error

View answer Workspace Report Error Discuss

Subject: Time and Work

2 2752
Q:

Two typists of varying skills can do a typing jobin6 minutesifthey work together.Ifthe first typist typed alone for 4 minutes and then the second typist typed alone for 6 minutes, they would be left with 1/5 of the whole work.Howmany minutes would it take the slower typist to complete the typing job working alone?

A) 10 minutes B) 15 minutes
C) 12 minutes D) 20 minutes
 
Answer & Explanation Answer: B) 15 minutes

Explanation:

Working efficiency of both typist together = 100/6 = 16.66%

Let the efficiency of first typist be x and second typist be (16.66 –x)

First typist for 4 minute + second tyoistfor 6 minute = 80% work

⇒4x + (16.66 –x) X 6 = 80%

⇒4x + 100% -6x = 80%,

⇒x = 10%

First typist typed 10% per minute, second typst typed (16.66 –10) = 6.66% per minute

Slowest is second typist complete whole job in 100/6.66 = 15.01 = 15 minute

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 2708
Q:

A and B do (3/5) th part of a work and the rest of the work is completed by C. If A, B and C take the same work for Rs 5000, then what is the share of C (in Rs)?

A) 3000 B) 2500
C) 2000 D) 1500
 
Answer & Explanation Answer: C) 2000

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2691
Q:

A can do 50% of the job in 16 days, B can do 1/4th of the job in 24 days. In how many days can they do 3/4th of the job working together?

A) 24 B) 9
C) 21 D) 18
 
Answer & Explanation Answer: D) 18

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

17 2682
Q:

70000 a year is how much an hour?

A) 80 B) 8
C) 0.8 D) 0.08
 
Answer & Explanation Answer: B) 8

Explanation:

Given for year = 70000

=> 365 days = 70000

=> 365 x 24 hours = 70000

=>   1 hour = ?

70000/365x24 = 7.990 = 8

Report Error

View Answer Report Error Discuss

3 2590