Q:

Project Integration Management

What are the Project Management Processes included in the Project Integration Management?

Answer

The Integrative Project Management Processes include:


Develop Project Charter - Developing the project charter that formally authorizes a project or a project Phase.


Develope Preliminary Project Scope Statement - Developing the preliminary project scope statement that provides a high level scope narrative


Develop Project Management Plan -  Documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans into a project management plan.


Direct and Manage Project Execution- Executing the work defined in the project management plan to achieve the project's requirements defined in the project scope statement.


Monitor and Control Project Work - Monitoring and controlling the processes used to initiate, plan, execute, and close a project to meet the performance objectives defined in the project management plan.


Integrated Change Control - Reviewing all change requests, approving changes, and controlling changes to the deliverables and organizational process assets.


Close Project - Finalizing all activities across all of the Project Management Process Groups to formally close the project or a Project phase.

Report Error

View answer Workspace Report Error Discuss

0 2927
Q:

During Mughal period there was continuous emigration of the .........to places ruled by Hindu Rajas

A) Nobles B) Poor
C) Middle Class D) Foreign residents
 
Answer & Explanation Answer: B) Poor

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History

0 2927
Q:

Which of the statements given below are correct?

 

A) In 2018 IPL auctions, Sunrisers Hyderabad retained Steve Smith.

B) Lewis Hamilton won the Formula One 2017 Japanese Grand Prix.

C) Ma Long won the 2017 San Marino and Rimini's Coast Motorcycle Grand Prix.

 

A) Only A B) Only B
C) A and C D) A and B
 
Answer & Explanation Answer: B) Only B

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Sports
Exam Prep: Bank Exams

1 2926
Q:

Which of the following group does NOT follow Newlands Law of Octaves?

 

A) Li, Na B) Be, Mg  
C) C, Si   D) Mn, Hg
 
Answer & Explanation Answer: D) Mn, Hg

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Chemistry
Exam Prep: Bank Exams

0 2926
Q:

Fuse Wire is Made of?

A) an alloy of Tin and Lead B) Nickel
C) Copper D) an alloy of Nickel and Lead
 
Answer & Explanation Answer: A) an alloy of Tin and Lead

Explanation:

Fuse Wire is Made of an alloy of Tin and Lead.

 

If too high a current flows, the element rises to a higher temperature and either directly melts, or else melts a soldered joint within the fuse, opening the circuit. Thefuse element is made of an alloy of Tin and Lead to provide stable and predictable characteristics.

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Analyst , Bank PO , Database Administration , IT Trainer

9 2926
Q:

Meteorology is the study of

 

A) The atmosphere B) Outer space
C) Landforms D) The oceans
 
Answer & Explanation Answer: A) The atmosphere

Explanation:

Meteorology is a branch of science that deals with the study of the atmosphere that focuses on weather processes and forecasting.

 

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: Bank Exams

0 2925
Q:

Management by projects views aspects of ongoing operations as projects in order to apply Project Management techniques to them. This can be used to describe an oranizational approach to the management of ongoing operations. Why would a company want to utilize this methodology on nonprojects?

A) To keep project managers employed B) To provide better estimates about durations
C) To allow the utilization of PM tools, such as earned value, to calculate ROI D) To specify the different phases within the operations
 
Answer & Explanation Answer: C) To allow the utilization of PM tools, such as earned value, to calculate ROI

Explanation:

Answer A is incorrect because project managers are not effectively utilized if they are always scheduling and coordinating resources for daily operations. Answer B is incorrect because project managers are not the best resource for providing estimates on daily operations and time allocations;people doing the actual work are the best resources. Answer D is incorrect because you do not specify different phases of ongoing operations.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 2925
Q:

Explain a.) Deceptive Ad b.) Unfair Ad

Answer

Deceptive Ad :


Deceptive advertising is also known as “False Advertising”. It is one form of advertising that will equip consumers with false and misleading information.


 


 


Unfair Ad :


Unfair advertising is very dangerous to consumers that involve legal binding. 


When there is an occurrence of public policy and consumer rights violation in an advertising message, then it is coined as “Unfair advertising”.  

Report Error

View answer Workspace Report Error Discuss

1 2925