Questions

Q:

The first Congress and nationalist leader to face repeated imprisonment was

A) Pheroze Shah Mehta B) BG Tilak
C) Gopal Krishna Gokhale D) Dadabhai Naoroji
 
Answer & Explanation Answer: B) BG Tilak

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History

5 4765
Q:

The 2016 black comedy crime thriller 'Udta Punjab' is loosely based on which of the following?

 

A) Wheat harvest in Punjab B) Drug abuse in Punjab
C) Child labour in Punjab D) Partition problems in Punjab
 
Answer & Explanation Answer: B) Drug abuse in Punjab

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: Bank Exams

0 4764
Q:

The valve present between left auricle and left ventricle is

A) Mitral B) Tricuspid
C) Semilunar D) Pulmonary
 
Answer & Explanation Answer: A) Mitral

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Biology

23 4763
Q:

Which new train is being flagged off by railway minister Suresh Prabhu in April 2017 ?

A) Double Deck Passenger Trains B) High-speed rail
C) Metro train D) Vistadome coach train
 
Answer & Explanation Answer: D) Vistadome coach train

Explanation:

Vistadome coach train flagged off in April 2017 is routed between Visakhapatnam to Araku valley station.

Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: Bank Exams , CAT
Job Role: Bank Clerk

4 4761
Q:

Which of the statements given below are not correct?

1. The author of the novel 'A Visit from the Goon Squad' is Edward P Jones.
2. The author of the novel 'The Corrections' is Jonathan Franzen.
3. The author of the novel 'The Known World' is Jennifer Egan.

A) 1 and 2 B) 2 and 3
C) 1 and 3 D) 1, 2 and 3
 
Answer & Explanation Answer: C) 1 and 3

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Books and Authors
Exam Prep: Bank Exams

1 4761
Q:

Controlling marketing activities :

What does monitoring and controlling marketing activities entail?

Answer

All those activities which have been planned out by the marketing department must be tried out in the market several times in order to be able to conclude if such activities are worthwhile or not. Such activities may be repeated several times over a period say six months or a year in order to be able to decide whether to stick to them or replace them with other better alternatives. Monitoring and controlling the marketing activities entails keeping proper records of the various activities and tracking them time and again particularly when it comes to the media, when to promote the product, cost factor, reach or the number of persons towards whom the promotions have been targeted, responses generated, sales generation and return on sales

Report Error

View answer Workspace Report Error Discuss

7 4761
Q:

Can you name the four days of the week that begin with the letter T?

Answer

Today, Tomorrow, Tuesday and Thursday.

Report Error

View answer Workspace Report Error Discuss

Subject: Logic Puzzles Exam Prep: Bank Exams

40 4761
Q:

Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction  phase of a project. you are currently in the process of activity sequencing. This is a example of what?

A) Gatekeeping B) Milestone
C) New scope for the project D) Project integration
 
Answer & Explanation Answer: B) Milestone

Explanation:

The approval by the Architecture Review Board is a milestone you want to include in activity sequencing so that you can ensure the requirements for meeting the review board's approval are met.  Answer A is tempting because the question references phase-end activities; however, it is not an example of gatekeeping because the project is not being authorized to continue based only on the architecture review.Gatekeeping often involves the review of other factors as well. Answer C is incorect because the requirement of a review board approval does not afect scope. Answer D is incorrect because project integration planning involves project plan development, execution, and integrated change control, which are not related to a review board.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification