Q:
You are a project manager for the redevelopment of the Hoover Dam. Your team has been provided with the scope statement, but it lacks many description details. Your team is concerned because the project is in the initiation phase and it wants to postpone it until it has more information. As the project manager, you recommend that
Answer & Explanation
Answer: C) The team should verify the scope and realize that more details will be available as more project characteristics are progressively elaborated.
Explanation: The project details and description will usually have less detail at the beginning of the project and will increase as the characteristics are progressively elaborated. Answer A is incorrect because the team should confirm that they understand the esence of the scope of the project, even if the details might be ambiguous at the beginning of the project. Answer B is incorrect because the project should go forward; however, the team should request further clarification of what the project scope entails. Answer D is incorrect because the project selection criteria should be established before the project begins.
View Answer
Report Error
Discuss