Subject matters experts (SMEs) are resources that are imperative to the succes of a project. Many times, project managers are not experts in the areas they are managing and frequently must rely upon other's expertise. In which scope - management process are SMEs first used?

A) Scope planning B) Scope definition
C) Initiation D) Scope verification
 
Answer & Explanation Answer: C) Initiation

Explanation:

Initiation is the first step in the scope management process, and expert judgment is one of the techniques routinely utilized. Answers A, B, and D are incorrect because they would come after the initiation process.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 3735
Q:

Which river has no mention in Rigaveda

A) Sindhu B) Saraswati
C) Yamuna D) Periyar
 
Answer & Explanation Answer: D) Periyar

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History

2 3735
Q:

When were the first general elections of Independent India conducted ?

A) 1948-49 B) 1949-50
C) 1950-51 D) 1951-52
 
Answer & Explanation Answer: D) 1951-52

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Politics

25 3735
Q:

N.R. Narayana Murthy was recently presented with the 2014  'Global India Award' in Canada. He is the executive chairman of which of the following companies?

A) Infosys B) Wipro
C) IBM D) TCS
 
Answer & Explanation Answer: A) Infosys

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness

1 3734
Q:

88%of 370 +24% of 210-x =118 find x

Answer

From the given equation,


88x370/100 + 24x210/100 - 118 = x


=> x = 325.6 + 50.4 - 118


x = 258.

Report Error

View answer Workspace Report Error Discuss

Subject: Database Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

7 3734
Q:

You are working on a new project to develop a new wireless product with ease - of - use features recommended by customers. It is as yet undetermined which features and the extent to which each feature will be incorporated into the product.You have a focus group that will continue to evaluate the features as the project goes forward.The focus group is authorized to suggest changes, as are your engineers and the quality department.As a project manager, what will help you most to minimize the effect of these changes?

A) A change management plan B) A scope management plan
C) Do not continue with the project until all of the features are clearly defined in the scope statement and scope definition. D) This is an expected part of every project. A good project manager will have a communications plan in place to be sure everyone knows what is happening on the project.
 
Answer & Explanation Answer: B) A scope management plan

Explanation:

Answer A is tempting because the problem focuses on changes. However, because we are talking about the elaboration of the product's characteristics, we are talking about scope changes, and therefore Answer B is the best answer. Answer C is also tempting because it is difficult to more forward on a project until the scope is clearly defined (especially in systems development projects), but with products and certain types of web development, scope changes can be frequent, and a formal scope management plan is needed. Answer D is true from a project perspective, but does not addres the scope issues.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 3734
Q:

 What item, originally called the ‘Whirlwind’, was invented by Ives McGaffey in 1869?

A) Blender B) Electric mixer
C) Washing machine D) Vacuum cleaner
 
Answer & Explanation Answer: B) Electric mixer

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Inventions

2 3734
Q:

India's first National Defence University is being established in

A) Gurgaon B) Hissar
C) Panipat D) Ambala
 
Answer & Explanation Answer: A) Gurgaon

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: Bank Exams
Job Role: Bank PO

2 3733