Questions

Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4875
Q:

Which of the following pair is CORRECT?


I. Summer Olympics 2020 - Tokyo
II. Summer Olympics 2016 - Rio de Janeiro
III. Summer Olympics 2012 - London

A) Only I and II B) Only I and III
C) Only II and III D) All are correct
 
Answer & Explanation Answer: D) All are correct

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Sports
Exam Prep: Bank Exams

2 4875
Q:

The vitamin that helps in blod clotting is 

A) Vitamin C B) Vitamin D
C) Vitamin E D) Vitamin K
 
Answer & Explanation Answer: D) Vitamin K

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness

6 4875
Q:

Consider the following statements in respect of financial emergency under Article 360 of the Constitution of India:

1. A proclamation of financial emergency issued shall cease to operate at the expiration of two months, unless, before the expiration of that period , it has been approved by the resolutions of both House of Parliament.

2. Financial Emergency can remain in operation for a maximum period of three years.

Which of the statement given above is / are correct?

A) 1 only B) 2 only
C) Both 1 and 2 D) None of these
 
Answer & Explanation Answer: C) Both 1 and 2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Politics

1 4874
Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 4874
Q:

DNA can be found in what Organelles?

A) Chloroplasts and Mitichondria B) Nucleus and Ribosomes
C) Ribosomes and Mitochondria D) Endoplasmic Reticulum and Nucleus
 
Answer & Explanation Answer: A) Chloroplasts and Mitichondria

Explanation:

DNA can be found in 3 Organelles namely Nucleus, Mitochondria in animals and Chloroplasts in plants.

Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank PO

15 4872
Q:

Who among the following was elected unanimously as the Secretary General of the UNO  for the second term?

A) Nelson Mandela B) Hillary R Clinton
C) Jacob Mathew D) Bank-Ki moon
 
Answer & Explanation Answer: D) Bank-Ki moon

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness

3 4872
Q:

The solution for all business needs is

A) RBI B) SCM
C) ERP D) EDI
 
Answer & Explanation Answer: C) ERP

Explanation:

The solution for all business needs is ERP (Enterprise resource planning).

 

the_solution_for_all_business_needs_is1553166104.png image

 

Enterprise resource planning (ERP) is business process management software that allows an organization to use a system of integrated applications to manage the business and automate many back office functions related to technology, services and human resources.

Report Error

View Answer Report Error Discuss

Filed Under: Business Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO