Q:
A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?
Answer & Explanation
Answer: D) Scope management plan.
Explanation: “The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”