Questions

Q:

Which of the following is not a function of the Control Unit?

A) Interpret instructions B) Read instructions
C) Execute instructions D) Direct operations
 
Answer & Explanation Answer: B) Read instructions

Explanation:

Control Unit can perform the functions Interpret instructions, Execute instructions and Direct operations. But Reading instructions is not a function of the Control Unit.

Report Error

View Answer Report Error Discuss

13 4884
Q:

Who among the following was elected unanimously as the Secretary General of the UNO  for the second term?

A) Nelson Mandela B) Hillary R Clinton
C) Jacob Mathew D) Bank-Ki moon
 
Answer & Explanation Answer: D) Bank-Ki moon

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness

3 4881
Q:

Which Commission made the recommendations which formed the basis for the Punjab Reorganisation Act which created the states Punjab and Haryana?

A) Dhar Commission B) Dass Commission
C) Shah Commission D) Mahajan Commission
 
Answer & Explanation Answer: C) Shah Commission

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Politics

5 4880
Q:

Consider the following statements in respect of financial emergency under Article 360 of the Constitution of India:

1. A proclamation of financial emergency issued shall cease to operate at the expiration of two months, unless, before the expiration of that period , it has been approved by the resolutions of both House of Parliament.

2. Financial Emergency can remain in operation for a maximum period of three years.

Which of the statement given above is / are correct?

A) 1 only B) 2 only
C) Both 1 and 2 D) None of these
 
Answer & Explanation Answer: C) Both 1 and 2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Politics

1 4880
Q:

Select the synonym of

 

to permeate

 

A) to desiccate B) to imbue
C)  torrid D) stale
 
Answer & Explanation Answer: B) to imbue

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 4879
Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4877
Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 4875
Q:

What Henry Bessemer invented?

A) Aluminum B) Electroplating
C) Steel Converter D) Steel rolling mill
 
Answer & Explanation Answer: C) Steel Converter

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Inventions

5 4875