Questions

Q:

Pushkalavati was capital of which of the following acient Kingdoms ?

A) Magadha B) Kashi
C) Gandhara D) Kosal
 
Answer & Explanation Answer: C) Gandhara

Explanation:

Pushkalavati was capital of ancient Kingdom of Gandhara. Its ruins are currently located in Charsadda, Pakistan, located in Peshawar valley in the Khyber Pakhtunkhwa province (formerly NWFP). Pushkalavati was home of the Sanskrit grammarian Panini.

Report Error

View Answer Report Error Discuss

Filed Under: Indian History
Exam Prep: Bank Exams

12 4884
Q:

Who among the following was elected unanimously as the Secretary General of the UNO  for the second term?

A) Nelson Mandela B) Hillary R Clinton
C) Jacob Mathew D) Bank-Ki moon
 
Answer & Explanation Answer: D) Bank-Ki moon

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness

3 4883
Q:

Which of the following is a function of money?

 

A) medium of exchange B) store of value
C) unit of accounting D) All options are correct
 
Answer & Explanation Answer: D) All options are correct

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Business Awareness
Exam Prep: Bank Exams

2 4882
Q:

Alloy of copper and zinc is called

A) Bronze B) Gold
C) Silver D) Brass
 
Answer & Explanation Answer: D) Brass

Explanation:

alloy_of_copper_and_zinc_is_called1556100441.jpg image

 

Alloy of copper and zinc is called as Brass.

Report Error

View Answer Report Error Discuss

Filed Under: Chemistry
Exam Prep: GATE , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

3 4882
Q:

What Henry Bessemer invented?

A) Aluminum B) Electroplating
C) Steel Converter D) Steel rolling mill
 
Answer & Explanation Answer: C) Steel Converter

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Inventions

5 4879
Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4878
Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 4877
Q:

Capital budgeting decisions are generally based on:

 

A) Tentative predictions of future outcomes. B) Perfect predictions of future outcomes.
C) Speculation of interest rates and economic performance only. D) Results from past outcomes only.
 
Answer & Explanation Answer: A) Tentative predictions of future outcomes.

Explanation: