Q:
The schedule performance index (SPI) is calculated as
Answer & Explanation
Answer: B) Earned Value(EV) divided by Planned Value (PV)
Explanation: Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance.