Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A, B and C can complete the work in 4, 5 and 6 hours respectively. If they all work together and receive Rs. 777 as wages then find the share of A.

A) Rs. 300 B) Rs. 315
C) Rs. 326 D) Rs. 175
 
Answer & Explanation Answer: B) Rs. 315

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

9 1079
Q:

P and Q can do a project in 20 and 12 days respectively. In how many days can they complete 40% of the project if they work together?

A) 1.5 days B) 3 days
C) 6 days D) 9 days
 
Answer & Explanation Answer: C) 6 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1077
Q:

24 men can do a piece of work in 17 days.How many men will be able to do it in 51 days ?

A) 8 B) 10
C) 12 D) 6
 
Answer & Explanation Answer: A) 8

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1071
Q:

A and B can together do a piece of work in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is

A) 18 days B) 24 days
C) 9 days D) 12 days
 
Answer & Explanation Answer: A) 18 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1065
Q:

A can make a cupboard in 10 days and B can do it in 50 days. Along with C, they did the job in 6.25 days only. Then in how many days C alone can do the job?

A) 20 B) 25
C) 16 D) 15
 
Answer & Explanation Answer: B) 25

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1062
Q:

Anil can do a piece of work in 14 days which Rohit can do in 21 days. They worked together for few days after which Anil left. If Rohit worked alone for 3 days, find the total number of days it took to complete the whole work.

A) 31/5 B) 51/5
C) 21/5 D) 13/5
 
Answer & Explanation Answer: B) 51/5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1062
Q:

If 15 persons can do a job in 30 days, then 30 persons with twice the efficiency can do the same job in how many days?

A) 7 B) 3.5
C) 5 D) 7.5
 
Answer & Explanation Answer: D) 7.5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1061
Q:

A can do a work in 12 days while B can do it in 15 days. They undertake to complete it together for Rs. 450. what will be the share of A in this amount of money ?

A) Rs.200 B) Rs.240
C) Rs.250 D) Rs.300
 
Answer & Explanation Answer: C) Rs.250

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1058