Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field ?

A) 9 B) 10
C) 6 D) 8
 
Answer & Explanation Answer: D) 8

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1574
Q:

Badki can bake 45 cakes in 9 hours, Badki and Chutki together can bake 80 cakes in 10 hours. How many cakes Chutki can bake in 40 hours?

A) 125 B) 10
C) 120 D) 20
 
Answer & Explanation Answer: C) 120

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams , CAT

0 1572
Q:

Manoj can do a piece of work in 42 hours. If he is joined by Jayashree who is 100% more efficient, in what time they will finish the work together?

A) 7 hours B) 3.5 hours
C) 14 hours D) 2.5 hours
 
Answer & Explanation Answer: C) 14 hours

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1567
Q:

Mandeep works 3 times as fast as Sampat. If Sampat can complete a job alone in 60 days, then in how many days can they together finish the job?

A) 7 days B) 4 days
C) 5 days D) 15 days
 
Answer & Explanation Answer: D) 15 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1562
Q:

9 women can complete a work in 50 days. If more 6 women were added to them, how many days before the work can be completed?

A) 30 B) 20
C) 15 D) 25
 
Answer & Explanation Answer: B) 20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

10 1558
Q:

A can do a work in 20 days and B in 50 days. If they work on it together for 5 days, then what fraction of work is left?

A) 13/20 B) 1/3
C) 1/6 D) 2/9
 
Answer & Explanation Answer: A) 13/20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1557
Q:

If 5 person together can make 5 mats in 5 hrs, then 10 person in 10 hours will make

A) 20 mats B) 10 mats
C) 15 mats D) 5 mats
 
Answer & Explanation Answer: A) 20 mats

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1551
Q:

Raman can do a work in 5 days, Jatin can do the same work in 7 days and Sachin can do the same work in 9 days. If they do the same work together and they are paid Rs 2860, then what is the share (in Rs) of Raman?

A) 1260 B) 700
C) 900 D) 870
 
Answer & Explanation Answer: A) 1260

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT

4 1550