Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Working alone A can do the task in 27 hours and B can do it in 54 hours. Find C's share (in Rs) if A, B and C get paid Rs 4,320 for completing a task in 12 hours on which they worked together.

A) 1440 B) 960
C) 1920 D) 1280
 
Answer & Explanation Answer: A) 1440

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1766
Q:

Ranjith can complete a task in 25 days while Anji can finish it in 20 days. They work together on the task for 5 days and then Ranjith leaves. In how many days will Anji finish the remaining work?

A) 15 days B) 10 days
C) 11 days D) 9 days
 
Answer & Explanation Answer: C) 11 days

Explanation:

Lcm of 25 and 20 is 100. So total work = 100 units
Ranjith can do 4 units per day while anju can do 5 units per day
They together complete 5 days of work i.e 9 x 5 = 45 units
The remaining 55 units of work is done by anju in 55/5 days (or) 11 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT

2 1736
Q:

Amit can complete a work in 25 days and Punit can complete the same work in 20 days. Punit alone worked at it for 10 days and then left the work. In how many days will Amit alone complete the remaining work?

A) 10.5 B) 11.5
C) 12.5 D) 13.5
 
Answer & Explanation Answer: C) 12.5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1736
Q:

A can paint a house in 45 days and B can do it in 15 days. Along with C, they did the job in 5 days only. Then, C alone can do the job in how many days?

A) 12 B) 9
C) 15 D) 8
 
Answer & Explanation Answer: B) 9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1734
Q:

X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part  of the total work?

 

A)  6 B) 4
C) 3 D) 12
 
Answer & Explanation Answer: B) 4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

8 1725
Q:

A can paint a house in 25 days and B can do it in 10 days. Along with C, they did the job in 6.25 days only. Then in how many days, C alone can do the job?

A) 50 B) 40
C) 30 D) 60
 
Answer & Explanation Answer: A) 50

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1723
Q:

Manish can complete a work in 21 days and Karan can complete the same work in 28 days. If both together work for 7 days, then what fraction of total work is left?

 

A) 3/5 B) 2/3
C) 7/12 D) 5/12
 
Answer & Explanation Answer: D) 5/12

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1722
Q:

Azhar is 4 times as good a workman as Balaraj and therefore is able to finish a job in 45 days less than Balaraj. Working together, they can do it in:

A) 6 days B) 18 days
C) 24 days D) 12 days
 
Answer & Explanation Answer: D) 12 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1715