Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Rohan and Mohit together can build a wall in 8 days. Mohit and Vikas build the same wall in 10 days and Vikas and Rohan can build the same wall in 12days. In how many days can all the three complete the same wall while working together?

A) 240/37 B) 120/37
C) 150/37 D) 180/37
 
Answer & Explanation Answer: A) 240/37

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1750
Q:

Painter 'A' can paint a house in 10 days and 'B' can do it in 20 days. With help of 'C', they did the job in 5 days only. Then, 'C' alone can do the job in:

A) 20 days B) 10 days
C) 40 days D) 50 days
 
Answer & Explanation Answer: A) 20 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1748
Q:

S, T and U can complete a work in 40, 48 and 60 days respectively. They received Rs 10800 to complete the work. They begin the work together but Tleft 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work alone. What is the share of S(in Rs) from total money?

A) 4320 B) 4500
C) 4860 D) 4960
 
Answer & Explanation Answer: C) 4860

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1736
Q:

50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

A) 36 B) 38
C) 40 D) 45
 
Answer & Explanation Answer: C) 40

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , Bank Exams
Job Role: Bank PO , Bank Clerk

3 1732
Q:

If A, B and C together do a job in 4 days, A and C together do the job in 4.5 days and B and C together do the job in 12 days then in how many days can C alone do the job?

A) 36 B) 6
C) 18 D) 12
 
Answer & Explanation Answer: C) 18

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1721
Q:

8 men can complete a work in 16 days. 16 women can complete the same work in 24 days. In how many days can 4 men and 8 women complete the same work?

A) B)
C) D)
 
Answer & Explanation Answer:

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

10 1719
Q:

Pannalal has done 1/3rd of a job in 20 days, Saiprasad completes the rest of the job in 10 days. In how many days can they together do the job?

A) 12 days B) 6 days
C) 3 days D) 24 days
 
Answer & Explanation Answer: A) 12 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT

4 1707
Q:

A and B can complete a task in 1.5 days. However, A had to leave a few days before the task wascompleted and hence it took 2 days in all to complete the task. If A alone could complete the work in2.625 days, how many days before the work getting over did A leave?

A) 1.125 B) 0.625
C) 0.375 D) 0.875
 
Answer & Explanation Answer: D) 0.875

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

13 1706