FACTS  AND  FORMULAE  FOR  CHAIN  RULE  QUESTIONS

 

 

1. Direct Proportion: Two quantities are said to be directly proportional, if on the increase (or decrease) of the one, the other increases (or decreases) to the same extent.

Ex. 1. Cost is directly proportional to the number of articles. (More Articles, More Cost)

Ex. 2. Work done is directly proportional to the number of men working on it (More Men, More Work)

 

2. Indirect Proportion: Two quantities are said to be indirectly proportional,if on the increase of the one, the other decreases to the same extent and vice-versa.

Ex. 1. The time taken by a car in covering a certain distance is inversely proportional to the speed of the car. (More speed, Less is the time taken to cover a distance)

Ex. 2. Time taken to finish a work is inversely proportional to the num of persons working at it. (More persons, Less is the time taken to finish a job)

Q:

If 7 spiders make 7 webs in 7 days, then 1 spider will make 1 web in how many days?

A) 1 B) 3
C) 7 D) 14
 
Answer & Explanation Answer: C) 7

Explanation:

Let the required number days be x.

Less spiders, More days (Indirect Proportion)

Less webs, Less days (Direct Proportion)

 Spiders1:7Webs7:1 7:x 

=> 1 * 7 * x = 7 * 1 * 7 

=> x= 7

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule

108 61310
Q:

39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work?

A) 10 B) 13
C) 14 D) 15
 
Answer & Explanation Answer: B) 13

Explanation:

Let the required number of days be x.

Less persons, More days (Indirect Proportion)

More working hours per day, Less days (Indirect Proportion)

Persons30:39Working hours/day6:5 12:x

 

=> 30 * 6 * x = 39 * 5 * 12 

 

=> x= 13

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule

56 56814
Q:

If 20 men can build a wall 56 meters long in 6 days , what length of  a similar wall can be  built by 35 men in 3 days?

A) 46 B) 47
C) 48 D) 49
 
Answer & Explanation Answer: D) 49

Explanation:

Let the required length be x meters

 More men, More length built     (Direct proportion) 

Less days, Less length built      (Direct Proportion)

Men20:35Days6 : 3 56 :x 

=> (20 x 6 x X)=(35 x 3 x 56) 

=> x = 49 

Hence, the required length is 49 m.

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule

153 49934
Q:

A certain number of men can finish a piece of work in 100 days. If there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?

A) 75 B) 82
C) 100 D) 110
 
Answer & Explanation Answer: D) 110

Explanation:

Originally let there be x men.

Less men, More days     (Indirect Proportion)

 Therefore, (x-10) : x  :: 100 :110

=> (x - 10) * 110 = x * 100    => x= 110

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule

96 44051
Q:

A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the begining and 100 more  after 35 days and completes the work in stipulated time. If he had not  engaged  the additional men, how many days  behind schedule would it be finished?

A) 3 B) 5
C) 6 D) 9
 
Answer & Explanation Answer: B) 5

Explanation:

[(100 x 35) + (200 x 5)]men can finish the work in 1 day 

Therefore, 4500 men can finish the work in 1 day. 100 men can finish it in  4500/100= 45 days.

This is 5 days behind Schedule

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule

64 37588
Q:

2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys can do the same in 11 days. Then, 8 men and 6 boys can do three times the amount of this work in 

A) 18 days B) 21 days
C) 24 days D) 30 days
 
Answer & Explanation Answer: B) 21 days

Explanation:

(2 x 14) men +(7 x 14) boys = (3 x 11) men + (8 x 11) boys

 =>5 men= 10 boys    => 1man= 2 boys

 Therefore, (2 men+ 7 boys) = (2 x 2 +7) boys = 11 boys

 

( 8 men + 6 boys) = (8 x 2 +6) boys = 22 boys.

 Let the required  number of days be x.

 More boys , Less days     (Indirect proportion)

 More work , More days    (Direct proportion)

 Boys22:11Work1 : 3 14:x

 Therefore, (22 * 1 * x) = (11 * 3 * 14)

=> x = 21 

Hence, the required number of days = 21

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule

90 35320
Q:

36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work ?

A) 24 days B) 28 days
C) 34 days D) 35 days
 
Answer & Explanation Answer: A) 24 days

Explanation:

Less Men, means more Days {Indirect Proportion}

Let the number of days be x then,

27 : 36 :: 18 : x


[Please pay attention, we have written 27 : 36 rather than 36 : 27, in indirect proportion, if you get it then chain rule is clear to you :)]                                

=>27x = 36 * 18

=> x = 24

 So 24 days will be required to get work done by 27 men.

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule

40 31039
Q:

3 pumps working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?

A) 9 B) 10
C) 11 D) 12
 
Answer & Explanation Answer: D) 12

Explanation:

Let the required no of working hours per day be x.

More pumps , Less working hours per day  (Indirect Proportion)

Less days, More working hours per day      (Indirect Proportion)

 Pumps4 : 3Days1 : 2 8:x

=> (4 * 1 * x) = (3 * 2 * 8)

=> x=12

Report Error

View Answer Report Error Discuss

Filed Under: Chain Rule

47 28947