Q:

Sumit is 28% less efficient than Amit. If Amit can make a wall in 54 days, then Sumit can complete the same work in how many days?

 

A) 75 B) 70
C) 72 D) 76
 
Answer & Explanation Answer: A) 75

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1977
Q:

Flight A usually takes 1 hour more than Flight B to travel a distance of 7200 km. Due to engine trouble speed of flight B falls by a factor of 1/6th, so it takes 36 minutes more than Flight A to complete the same journey? What is the speed of Flight A (in km/hr)?

A) 800 B) 900
C) 750 D) 720
 
Answer & Explanation Answer: A) 800

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: Bank Exams

3 1976
Q:

A man travels 800 km in partly by rail and partly by steamer. He spends 7 hours more time on steamer. If the velocity of the steamer is 20 km/hr and the velocity of rail is 55 km/hr, how much distance does he cover by steamer?

A) 316 km B) 379 km
C) 474 km D) 569 km
 
Answer & Explanation Answer: A) 316 km

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: Bank Exams

3 1976
Q:

The average of fruits offered in a temple in a week was 75. The average of fruits offered in six days excluding Tuesday was 72. How many fruits were offered on Tuesday?

A) 90 B) 93
C) 72 D) 92
 
Answer & Explanation Answer: B) 93

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Average

1 1976
Q:

Excluding stoppages, the speed of a bus is 72 kmph and including stoppages, it is 60 kmph. For how many minutes does the bus stop per hour?

A) 12 B) 8
C) 15 D) 10
 
Answer & Explanation Answer: D) 10

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: Bank Exams

4 1975
Q:

Profit of Rs 135200 has to be divided among three partners Aashay, Bhairav and Chetan in the ratio 4:3:6. How much Rs. does Chetan get?

A) 31200 B) 41600
C) 62400 D) 93600
 
Answer & Explanation Answer: C) 62400

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Partnership
Exam Prep: Bank Exams

3 1975
Q:

(251+252+253+254+255) is divided by

A) 23 B) 58
C) 124 D) 127
 
Answer & Explanation Answer: C) 124

Explanation:
Report Error

View Answer Report Error Discuss

0 1975
Q:

Simplify the equation 0.733+0.2730.732+0.272-0.73×0.27

A) 1 B) 0.4087
C) 0.73 D) 0.27
 
Answer & Explanation Answer: A) 1

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1975