Quantitative Aptitude - Arithmetic Ability Questions

Q:

If side of a square is increased by 60%, then what will be the percentage increase in its area?

 

 

A) 156 B) 120
C) 126 D) 132
 
Answer & Explanation Answer: A) 156

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

1 34494
Q:

Select the figure that does not belong in the following group.

 

 

 

A) D B) B
C) C D) A
 
Answer & Explanation Answer: C) C

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

2 34431
Q:

Find the odd one out.

 

 

A) 4 B) 3
C) 2 D) 1
 
Answer & Explanation Answer: A) 4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

0 34396
Q:

What is the probability of getting 53 Mondays in a leap year?

A) 1/7 B) 3/7
C) 2/7 D) 1
 
Answer & Explanation Answer: C) 2/7

Explanation:

1 year = 365 days . A leap year has 366 days

A year has 52 weeks. Hence there will be 52 Sundays for sure.

52 weeks = 52 x 7 = 364days

366 – 364 = 2 days

In a leap year there will be 52 Sundays and 2 days will be left.

These 2 days can be:

1. Sunday, Monday

2. Monday, Tuesday

3. Tuesday, Wednesday

4. Wednesday, Thursday

5. Thursday, Friday

6. Friday, Saturday

7. Saturday, Sunday

Of these total 7 outcomes, the favourable outcomes are 2.

Hence the probability of getting 53 days = 2/7

Report Error

View Answer Report Error Discuss

Filed Under: Probability

148 34375
Q:

If the numerator of a fraction is increased by 150% and the denominator of the fraction is increased by 350%, the resultant fraction is 25/51. What is the original fraction ?

A) 31/25 B) 15/17
C) 14/25 D) 11/16
 
Answer & Explanation Answer: B) 15/17

Explanation:

The original fraction is  2551 × 350+100150+100  = 15/17.

Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

61 34337
Q:

In a History examination, the average for the entire class was 80 marks. If 10% of the students scored 35 marks and 20% scored 90 marks, what was the average marks of the remaining students of the class ?

A) 25 B) 50
C) 75 D) 100
 
Answer & Explanation Answer: C) 75

Explanation:

Let the number of students in the class be 100 and let this required average be x.

Then, (10 * 95) + (20 * 90) + (70 * x) = (100 * 80)

=> 70x = 8000 - (950 + 1800) = 5250

=> x = 75.

Report Error

View Answer Report Error Discuss

Filed Under: Percentage

113 34252
Q:

A and  B can do  a piece of work in 30 days , while  B and C can do the same work in 24 days and C and A in 20 days . They all work together for 10 days when B and C leave. How many days more will A take to finish  the work?

A) 18 days B) 24 days
C) 30 days D) 36 days
 
Answer & Explanation Answer: A) 18 days

Explanation:

2(A+B+C)'s 1 day work = 1/30 + 1/24 + 1/20 = 1/8

=>(A+B+C)'s  1 day's work= 1/16

work done by A,B and C in 10 days=10/16 = 5/8

Remaining work= 3/8

A's 1 day's work= 116-124=148

Now, 1/48 work is done by A in 1 day.

 So, 3/8 work  wil be done by A in =48 x (3/8) = 18 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

138 34213
Q:

(x-2) men can do a piece of work in x days and (x+7) men can do 75% of the same work in (x-10)days. Then in how many days can (x+10) men finish the work?

A) 27 days B) 12 days
C) 25 days D) 18 days
 
Answer & Explanation Answer: B) 12 days

Explanation:

34×(x-2)x=(x+7)(x-10)

x2-6x-280 =0 

=> x= 20   and   x=-14

 so, the acceptable values is x=20 

Therefore, Total work =(x-2)x = 18 x 20 =360 unit

 Now   360 = 30 x k         

=> k=12 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

77 34203