Quantitative Aptitude - Arithmetic Ability Questions

Q:

A works twice as fast as B.If  B can complete a work in 18 days independently,the number of days  in which A and B can together finish the work is:

A) 4 days B) 6 days
C) 8 days D) 10 days
 
Answer & Explanation Answer: B) 6 days

Explanation:

Ratio of rates of working of A and B =2:1. So, ratio of times taken =1:2

Therefore, A's 1 day's work=1/9 

B's 1 day's work=1/18 

(A+B)'s 1 day's work= 1/9 + 1/18 = 1/6

so, A and B together can finish the work in 6 days

 

 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

101 34644
Q:

Out of 9 persons, 8 persons spent Rs. 30 each for their meals. The ninth one spent Rs. 20 more than the average expenditure of all the nine. The total money spent by all of them was : 

A) Rs. 292.50 B) Rs. 297.50
C) Rs. 298 D) Rs. 298.50
 
Answer & Explanation Answer: A) Rs. 292.50

Explanation:

Let the average expenditure be Rs. x Then,

 

9x=[(8*30)+(x+20)]<=>9x =x+260 <=> x =32.50

 

Total money spent = 9x =  Rs. (9 x 32.5O) = Rs 292. 50

Report Error

View Answer Report Error Discuss

Filed Under: Average

95 34594
Q:

Two trains started at the same time, one from A to B and the other from B to A . If they arrived at B and A respectively 4 hours and 9 hours after they passed each other the ratio of the speeds of the two trains was 

A) 2:1 B) 3:2
C) 4:3 D) 5:4
 
Answer & Explanation Answer: B) 3:2

Explanation:

Note : If two trains (or bodies) start at the same time from points A and B towards each other and after crossing they take a and b sec in reaching B and A respectively, then: (A's speed) : (B's speed) = (b : a)

Therefore, Ratio of the speeds of two trains = 9:4 = 3 : 2

Report Error

View Answer Report Error Discuss

Filed Under: Problems on Trains
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Bank Clerk , Bank PO

76 34564
Q:

What is the probability of getting 53 Mondays in a leap year?

A) 1/7 B) 3/7
C) 2/7 D) 1
 
Answer & Explanation Answer: C) 2/7

Explanation:

1 year = 365 days . A leap year has 366 days

A year has 52 weeks. Hence there will be 52 Sundays for sure.

52 weeks = 52 x 7 = 364days

366 – 364 = 2 days

In a leap year there will be 52 Sundays and 2 days will be left.

These 2 days can be:

1. Sunday, Monday

2. Monday, Tuesday

3. Tuesday, Wednesday

4. Wednesday, Thursday

5. Thursday, Friday

6. Friday, Saturday

7. Saturday, Sunday

Of these total 7 outcomes, the favourable outcomes are 2.

Hence the probability of getting 53 days = 2/7

Report Error

View Answer Report Error Discuss

Filed Under: Probability

148 34394
Q:

If the numerator of a fraction is increased by 150% and the denominator of the fraction is increased by 350%, the resultant fraction is 25/51. What is the original fraction ?

A) 31/25 B) 15/17
C) 14/25 D) 11/16
 
Answer & Explanation Answer: B) 15/17

Explanation:

The original fraction is  2551 × 350+100150+100  = 15/17.

Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

61 34348
Q:

What will come in place of the question mark in the series below?

7, 4.5, 5.5, 12, 49, ?

A) 393 B) 396
C) 354 D) 367
 
Answer & Explanation Answer: A) 393

Explanation:

Ans. 
4.5 = 7 x 0.5 + 1
5.5 = 4.5 x 1 + 1
12 = 5.5 x 2 + 1
49 = 12 x 4 + 1
? = 49 x 8 + 1, i.e. ? = 393

Report Error

View Answer Report Error Discuss

Filed Under: Numbers
Exam Prep: AIEEE , Bank Exams , GATE

2 34298
Q:

In a History examination, the average for the entire class was 80 marks. If 10% of the students scored 35 marks and 20% scored 90 marks, what was the average marks of the remaining students of the class ?

A) 25 B) 50
C) 75 D) 100
 
Answer & Explanation Answer: C) 75

Explanation:

Let the number of students in the class be 100 and let this required average be x.

Then, (10 * 95) + (20 * 90) + (70 * x) = (100 * 80)

=> 70x = 8000 - (950 + 1800) = 5250

=> x = 75.

Report Error

View Answer Report Error Discuss

Filed Under: Percentage

113 34268
Q:

A and  B can do  a piece of work in 30 days , while  B and C can do the same work in 24 days and C and A in 20 days . They all work together for 10 days when B and C leave. How many days more will A take to finish  the work?

A) 18 days B) 24 days
C) 30 days D) 36 days
 
Answer & Explanation Answer: A) 18 days

Explanation:

2(A+B+C)'s 1 day work = 1/30 + 1/24 + 1/20 = 1/8

=>(A+B+C)'s  1 day's work= 1/16

work done by A,B and C in 10 days=10/16 = 5/8

Remaining work= 3/8

A's 1 day's work= 116-124=148

Now, 1/48 work is done by A in 1 day.

 So, 3/8 work  wil be done by A in =48 x (3/8) = 18 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

138 34220