Quantitative Aptitude - Arithmetic Ability Questions

Q:

Select the odd word/letters/number/number pair from the given alternatives.

A) 532 B) 413
C) 111 D) 541
 
Answer & Explanation Answer: C) 111

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

0 1643
Q:

In ΔPQR, S and T are points on side PQ and PR respectively. ST is parallel to QR. If S divides PQ in the ratio 4:1 and length of QR is 15 cm,what is the length of ST?

A) 3 cm B) 5 cm
C) 12 cm D) 10 cm
 
Answer & Explanation Answer: C) 12 cm

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1643
Q:

If 4x + 3y = 11 and 3x + 2y = 8, then (x,y) is

A) 2, 0 B) 1, 6
C) 2, 1 D) 5, 6
 
Answer & Explanation Answer: C) 2, 1

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1643
Q:

If 3x + 4(1-x) > 5x -2 > 3x - 4; then the value of x is

A) 2 B) -2
C)  0 D) -3
 
Answer & Explanation Answer: C)  0

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1642
Q:

In the following question, four number pairs are given. The number on left side of (–) is related to the number on the right side of (–) with some Logic/Rule/Relation. Three are similar on basis of same Logic/Rule/Relation. Select the odd one out from the given alternatives.

A) 16 – 5 B) 24 – 6
C) 32 – 8 D) 88 – 22
 
Answer & Explanation Answer: A) 16 – 5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

0 1642
Q:

If the shopkeeper sells an item at Rs 450 which is marked as Rs 600, then what is the discount he is offering?

A) 33.33 percent B) 25 percent
C) 20 percent D) 30 percent
 
Answer & Explanation Answer: B) 25 percent

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

0 1642
Q:

A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in

A) 8 days B) 16 days
C) 30 days D) 32 days
 
Answer & Explanation Answer: B) 16 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1642
Q:

A man covered a certain distance by a train at the speed of 40 km/hr and covers the same distance back by walking at the speed of 8 km/hr. Ifthe whole journey took 12 hours, then what is the one side distance (in km)?

A) 80 B) 60
C) 90 D) 100
 
Answer & Explanation Answer: A) 80

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Problems on Trains
Exam Prep: Bank Exams

0 1642