Quantitative Aptitude - Arithmetic Ability Questions

Q:

In these tests find the Odd figure out

A) a B) b
C) c D) d
 
Answer & Explanation Answer: D) d

Explanation:

In all the squares, the direction of open face of all inner one is in different direction. But in option D there is 2 open face that faces the same direction i.e. south direction

Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

0 1571
Q:

Select the odd word/letters/number/number pair from the given alternatives.

A) JPM B) DJG
C) BHE D) SDA
 
Answer & Explanation Answer: D) SDA

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

1 1571
Q:

The ratio between the speeds of two buses is 11:9. If the second bus runs 270 kms in 15 hours, then the speed of the first bus is?

A) 23 km/hr B) 11 km/hr
C) 2 km/hr D) 22 km/hr
 
Answer & Explanation Answer: D) 22 km/hr

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: Bank Exams

2 1571
Q:

Chandan travelled equal distance with speed of 3 kmph, 4 kmph and 8kmph and takes a total time of 42.5 min. Find the total distance in km.

A) 4 B) 2
C) 1 D) 3
 
Answer & Explanation Answer: D) 3

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: Bank Exams

3 1571
Q:

10 persons can do a job in X days. If 20 persons with twice the efficiency can do the same job in 5 days, then find the value of X?

A) 40 B) 15
C) 20 D) 30
 
Answer & Explanation Answer: C) 20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1571
Q:

X does 25% of a work in 20 days. Y joins X and they together finish the remaining work in 15 days. Y alone can do the whole work in ___ days.

 

A) 30 days B) 25 1/2 days
C) 26 2/3 days D) 26 1/5 days
 
Answer & Explanation Answer: C) 26 2/3 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1571
Q:

24 men can do a piece of work in 17 days.How many men will be able to do it in 51 days ?

A) 8 B) 10
C) 12 D) 6
 
Answer & Explanation Answer: A) 8

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1570
Q:

A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days will A, B and C finish it, working all together?

A) 6 days B) 5 1/4 days
C) 4 4/11 days D) 4 days
 
Answer & Explanation Answer: D) 4 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1570