Quantitative Aptitude - Arithmetic Ability Questions

Q:

If U = 450 and V = 585, then V is how much percentage more than U?

A) 130 B) 23.07
C) 25 D) 30
 
Answer & Explanation Answer: D) 30

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

8 1755
Q:

The length of a rectangle is increased by 25%. To maintain the same area, the breadth has to be decreased by

A) 20% B) 25%
C) 30% D) 40%
 
Answer & Explanation Answer: A) 20%

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

1 1755
Q:

The length and breadth of a rectangle are 24 cm and 7 cm respectively. Calculate its perimeter (in cm).

A) 124 B) 48
C) 62 D) 96
 
Answer & Explanation Answer: C) 62

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

0 1754
Q:

ΔABC is right angled at B. BD is an altitude. AD = 9 cm and DC = 16 cm. What is the value of BD (in cm)?

A) 6 B) 18
C) 21 D) 12
 
Answer & Explanation Answer: D) 12

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

0 1754
Q:

If (x - 4) (x2 + 4x + 16) = x3 - P, then P is equal to

A) 27 B) 8
C) 64 D) 0
 
Answer & Explanation Answer: C) 64

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1754
Q:

In the following question, select the odd word pair from the given alternatives.

A) Length – Metre B) Temperature – Degree
C) Ampere – Current D) Work – Joule
 
Answer & Explanation Answer: C) Ampere – Current

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

1 1754
Q:

The average of 15 numbers is 7. If the average of the first 8 numbers is 6.5 and the average of the last 8 numbers is 8.5 then middle number is

A) 10 B) 23
C) 13 D) 15
 
Answer & Explanation Answer: D) 15

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Average
Exam Prep: Bank Exams

1 1754
Q:

30 men can do a piece of work in 16 days working 8 hrs a day. How many men are needed to complete another work, which is twice the first one, in 10 days working 12 hrs a day?

 

The following are the steps involved in solving the above problem. Arrange them in sequential order.

 

 

A) CBAD B) BACD
C) ABCD D) ACBD
 
Answer & Explanation Answer: A) CBAD

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1754