Q:

Find measure of central angle of the sector whose perimeter is 25 cm and radius of the circle is 7 cm?

A) 45° B) 22.5°
C) 135° D) 90°
 
Answer & Explanation Answer: D) 90°

Explanation:
Report Error

View Answer Report Error Discuss

0 1572
Q:

Product of digits of a 2-digit number is 15. If we add 18 to the number, the new number obtained is a number formed by interchange of the digits. Find the number.

A) 35 B) 15
C) 51 D) 21
 
Answer & Explanation Answer: A) 35

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Problems on Numbers
Exam Prep: Bank Exams

0 1572
Q:

Junko sold an item for Rs. 220 at a loss of 12%. By how much should she have raised the price to make a profit of 10% ?

A) Rs. 25 B) Rs. 48.40
C) Rs. 44 D) Rs. 55
 
Answer & Explanation Answer: D) Rs. 55

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Profit and Loss
Exam Prep: Bank Exams

0 1572
Q:

Karan, Arjun, Preeti, Priya and Ashish are travelling in a car. Three years ago, the average age of Arjun, Preeti and Priya was 42 years. If the present age of Karan is 65 years and the present average age of all five is 50 years, then what is the present age of Ashish?

A) 50 years B) 60 years
C) 70 years D) 80 years
 
Answer & Explanation Answer: A) 50 years

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Problems on Ages
Exam Prep: Bank Exams

1 1572
Q:

The average of 9 observations was found to be 35. Later on, it was detected that an observation 81 was misread as 18. The correct average of the observations is

A) 28 B) 42
C) 35 D) 45
 
Answer & Explanation Answer: B) 42

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Average
Exam Prep: Bank Exams

0 1572
Q:

If X=32, then the value of 27x3-54x2+36x-11 is

A) 1138 B) 1158
C) 1238 D) 1258
 
Answer & Explanation Answer: D) 1258

Explanation:
Report Error

View Answer Report Error Discuss

0 1571
Q:

A can do a work in 36 days and B in 12 days. If they work on it together, then in how many days will they be able to do the work?

A) 8 B) 6
C) 10 D) 9
 
Answer & Explanation Answer: D) 9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1571
Q:

30 men can do a piece of work in 16 days working 8 hrs a day. How many men are needed to complete another work, which is twice the first one, in 10 days working 12 hrs a day?

 

The following are the steps involved in solving the above problem. Arrange them in sequential order.

 

 

A) CBAD B) BACD
C) ABCD D) ACBD
 
Answer & Explanation Answer: A) CBAD

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1571