Quantitative Aptitude - Arithmetic Ability Questions

Q:

The area and the length of one of the diagonals of a rhombus is 84 cm² and 7 cm respectively. Find the length of its other diagonal (in cm).

A) 12 B) 24
C) 48 D) 36
 
Answer & Explanation Answer: B) 24

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

1 1408
Q:

In the following question, select the odd word from the given alternatives.

A) CEAC B) FHDF
C) PRMP D) TVRT
 
Answer & Explanation Answer: C) PRMP

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

1 1408
Q:

If x + y = 12 and xy = 32, then what is the value of  x2 + y2 ?

A) 24 B) 144
C) 128 D) 80
 
Answer & Explanation Answer: D) 80

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1408
Q:

A wholesaler sells a watch to a retailer at a profit of 33% and the retailer sells it to a customer at a loss of 20%. If the customer pays Rs 2,181.2, what had it cost the wholesaler?

A) Rs 2050 B) Rs 2320
C) Rs 2712 D) Rs 1780
 
Answer & Explanation Answer: A) Rs 2050

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Profit and Loss
Exam Prep: Bank Exams

4 1408
Q:

A wholesaler sells a good to a retailer at a profit of 5% and the retailer sells it to a customer at a profit of 10%. If the customer pays Rs. 2,000, what had it cost (in Rs) the wholesaler?

A) 1731.6 B) 3210.6
C) 1931.6 D) 2310.6
 
Answer & Explanation Answer: A) 1731.6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Profit and Loss
Exam Prep: Bank Exams

2 1406
Q:

35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is

A) 20 B) 35
C) 30 D) 25
 
Answer & Explanation Answer: D) 25

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1406
Q:

Parimal has done 1/4th of a job in 10 days, Salim completes the rest of the job in 20 days. In how many days can they together do the job?

A) 8 days B) 24 days
C) 12 days D) 16 days
 
Answer & Explanation Answer: D) 16 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 1406
Q:

If C = 1200 and D = 1500, then D is how much percent more than C?

A) 20 B) 33.33
C) 25 D) 125
 
Answer & Explanation Answer: C) 25

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

1 1406