Quantitative Aptitude - Arithmetic Ability Questions

Q:

Simplify : (25)32

 

A) 625 B) 15625
C) 125 D) √125
 
Answer & Explanation Answer: C) 125

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 78742
Q:

Find the odd one out of the following number series?

56, 64, 48, 90, 16, 144

 

A) 48 B) 64
C) 90 D) 16
 
Answer & Explanation Answer: C) 90

Explanation:

The given number series follows a pattern that,

56

56 + 8 = 64

64 - 16 = 48

48 + 32 = 80 (Not equal to 90)

80 - 64 = 16

16 + 128 = 144 

 

Hence, the odd number in the given number series is 90.

Report Error

View Answer Report Error Discuss

4 78738
Q:

If 0.75: x :: 5:8, then x is equal to:

A) 1.12 B) 1.16
C) 1.20 D) 1.30
 
Answer & Explanation Answer: C) 1.20

Explanation:

(x * 5) = (0.75 *8)

X=6/5 = 1.20

Report Error

View Answer Report Error Discuss

Filed Under: Ratios and Proportions

268 78671
Q:

Fill in the blanks

sinA = _____ x cosA

 

A) sinA B) tanA
C) cotA D) cosA
 
Answer & Explanation Answer: B) tanA

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

1 78350
Q:

Find the missing number in the series

1, 6,  ?, 15, 45, 66, 91

A) 24 B) 28
C) 32 D) 26
 
Answer & Explanation Answer: B) 28

Explanation:

Here the given series 1, 6,  ?, 15, 45, 66, 91 follows a

Pattern in the series is, +5, +9, +13,...,.. +21, +25

So +4 is getting increased at every term addition.

Missing Number in the series will be 15+(9+4) = 15 + 13 = 28.

Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO , IT Trainer

7 78194
Q:

12 men can complete a work in 8 days. 16 women can complete the same work in 12 days. 8 men and 8 women started working  and worked for 6 days. How many more men are to be added to complete the remaining work in 1 day?

A) 8 B) 12
C) 16 D) 24
 
Answer & Explanation Answer: B) 12

Explanation:

1 man's 1 day work =1/96 ; 1 woman's 1 day work = 1/192

Work done in 6 days=6896+8192=6×18 =34 

Remaining work = 1/4

(8 men +8 women)'s 1 day work = 1896+8192 =1/8

Remaining work =1/4 -  1/8 = 1/8

 

 1/96 work is done in 1 day by 1 man

 

Therefore, 1/8 work will be done in 1 day by 96 x (1/8) =12 men

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

326 78018
Q:

At what rate percent per annum will a sum of money double in 8 years.

A) 12.5% B) 13.5%
C) 11.5% D) 14.5%
 
Answer & Explanation Answer: A) 12.5%

Explanation:

Let principal = P, Then, S.I.= P and Time = 8 years

 

We know that S.I. = PTR/100

 

Rate = [(100 x P)/ (P x 8)]% = 12.5% per annum.

Report Error

View Answer Report Error Discuss

Filed Under: Simple Interest
Exam Prep: GRE , CAT , Bank Exams
Job Role: Bank PO , Bank Clerk

469 78008
Q:

Calculate the area (in sq.cm) of a circle whose diameter is 14 cm.

 

A) 154 B) 308
C) 224 D) 448
 
Answer & Explanation Answer: A) 154

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

1 77838