Q:
In the Determine Budget processes the project schedule
Answer & Explanation
Answer: C) is used to assign costs to the time period when the costs will be incurred
Explanation: “This [project schedule] information can be used to aggregate costs to the calendar periods when the costs are planned to be incurred.” PMBOK [7.2.1.4]