Q:
A) 3 days | B) 2 days |
C) 6 days | D) 12 days |
Answer: C) 6 days
Explanation:
Explanation:
From the given data,
12 children 16 days work,
One child’s one day work = 1/192.
8 adults 12 days work,
One adult’s one day’s work = 1/96.
Work done in 3 days = ((1/96) x 16 x 3) = 1/2
Remaining work = 1 – 1/2 = 1/2
(6 adults+ 4 children)’s 1 day’s work = 6/96 + 4/192 = 1/12
1/12 work is done by them in 1 day.
1/2 work is done by them in 12 x (1/2) = 6 days.