Q:
A,B,C can complete a work in 15,20 and 30 respectively.They all work together for two days then A leave the work,B and C work some days and B leaves 2 days before completion of that work.how many days required to complete the whole work?
Answer
Given A,B,C can complete a work in 15,20 and 30 respectively.
The total work is given by the LCM of 15, 20, 30 i.e, 60.
A's 1 day work = 60/15 = 4 units
B's 1 day work = 60/20 = 3 units
C's 1 day work = 60/30 = 2 units
(A + B + C) worked for 2 days = (4 + 3 + 2) 2 = 18 units
Let B + C worked for x days = (3 + 2) x = 5x units
C worked for 2 days = 2 x 2 = 4 units
Then, 18 + 5x + 4 = 60
22 + 5x = 60
5x = 38
x = 7.6
Therefore, total number of days taken to complete the work = 2 + 7.6 + 2 = 11.6 = 11 3/5 days.
View answer
Workspace
Report Error
Discuss