A and B can do a piece of work in 30 days , while B and C can do the same work in 24 days and C and A in 20 days . They all work together for 10 days when B and C leave. How many days more will A take to finish the work?
Answer & Explanation
Answer: A) 18 days
Explanation: 2(A+B+C)'s 1 day work = 1/30 + 1/24 + 1/20 = 1/8
=>(A+B+C)'s 1 day's work= 1/16
work done by A,B and C in 10 days=10/16 = 5/8
Remaining work= 3/8
A's 1 day's work=
Now, 1/48 work is done by A in 1 day.
So, 3/8 work wil be done by A in =48 x (3/8) = 18 days