1
Q:

Rohit crosses a 700 metres wide road in 35 seconds. What is his speed (in km/hr)?

 

A) 54 B) 76
C) 72 D) 84

Answer:   C) 72



Explanation:
Subject: Time and Work
Exam Prep: Bank Exams
Q:

At Arihant Prakasham every book goes hrough 3 phases (or stages) typing, composing and binding. There are 16 typists, 10 composers and 15 binders. A typist can type 8 books in each hour, a composer can compose 12 books in each hour and a binder can bind 12 books in each hour. All of the people at Arihant Prakasham works for 10 hours a day and each person is trained to do only the ob of 1 category.How many books can be prepared in each day?

A) 1500 B) 1200
C) 1440 D) 1380
 
Answer & Explanation Answer: B) 1200

Explanation:

T                 C              B

16              10             15

8                12             12

128            120           180             <------- in one hour

1280          1200         1800            <------- in 10 hours

Since, restriction is imposed by composers i.e,since only 1200 books can be composed i 10 hours so not more than 1200 books can be finally pepared.

 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

8 7803
Q:

Kaushalya can do a work in 20 days, while kaikeyi can do the same work in 25 days. They started the work jointly.Few days later Sumitra also joined them and thus all of them completed the whole work in 10 days. All of them were paid total Rs.700. What is the Share of Sumitra?

A) Rs.130 B) Rs.185
C) Rs.70 D) can't be determined
 
Answer & Explanation Answer: C) Rs.70

Explanation:

Efficiency of kaushalya = 5%

Efficiency of kaikeyi  = 4%

Thus, in 10 days working together they will complete only 90% of the work.

          [(5+4)*10] =90

Hence, the remaining work will surely done by sumitra, which is 10%.

Thus, sumitra will get 10% of Rs. 700, which is Rs.70

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

12 13490
Q:

A is twice efficient as B and together they do the same work in as much time as C and D together. If C and D can complete the work in 20 and 30 daysrespectively, working alone ,then in how many days A can complete the work individually:

A) 12 days B) 18 days
C) 24 days D) 30 days
 
Answer & Explanation Answer: B) 18 days

Explanation:

                                              A     +      B        =      C     +     D 

                                              |              |                 |             | 

    Ratio of efficiency         10x   +    5x               9x     +   6x 

                                             |________|                 |_________|   

                                                   15x                           15x 

Therefore , ratio of efficiency of A:C  =10:9 

Therefore,  ratio of days taken by A:C = 9:10 

Therefore, number of days taken by A = 18 days                 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

54 23605
Q:

(x-2) men can do a piece of work in x days and (x+7) men can do 75% of the same work in (x-10)days. Then in how many days can (x+10) men finish the work?

A) 27 days B) 12 days
C) 25 days D) 18 days
 
Answer & Explanation Answer: B) 12 days

Explanation:

34×(x-2)x=(x+7)(x-10)

x2-6x-280 =0 

=> x= 20   and   x=-14

 so, the acceptable values is x=20 

Therefore, Total work =(x-2)x = 18 x 20 =360 unit

 Now   360 = 30 x k         

=> k=12 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

77 31566
Q:

When A, B and C are deployed for a task , A and B together do 70% of the work and B and C together do 50% of the work. who is most efficient?

A) A B) B
C) C D) can't be determined
 
Answer & Explanation Answer: A) A

Explanation:

A + B= 70%   

B + C =50%   

  (A+B)+(B+C)-(A+B+C)= B

=> B= 20%     A= 50%        and   C=30%

Hence A is most efficient

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

31 18869
Q:

The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is:

A) 4.5 B) 5
C) 6 D) 9 1/3
 
Answer & Explanation Answer: C) 6

Explanation:

                       A   :   C    

 

Efficiency      5    :   3    

 

No of days   3x   :  5x     

 

Given that, 5x-6 =3x  => x = 3  

 

Number of days taken by A = 9  

 

Number of days taken by C = 15     

 

 

 

           B  :  C    

 

Days   2  :  3  

 

Therefore, Number of days taken by B = 10   

 

Work done by B and C in initial 2 days = 2110+115= 1/3  

 

Thus,  Rest work =2/3  

 

Number of days required by A to finish 2/3 work = (2/3) x 9 = 6 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

81 30164
Q:

A is thrice efficient as B and C is twice as efficient as B. what is the ratio of number of days taken by A,B and C, when they work individually?

A) 2:6:3 B) 2:3:6
C) 1:2:3 D) 3:1:2
 
Answer & Explanation Answer: A) 2:6:3

Explanation:

                                                A    :    B    :    C   

Ratio of efficiency               3     :    1    :    2   

Ratio of No.of days            1/3  :   1/1  :   1/2    

     or                                       2    :    6    :    3   

Hence A is correct.  

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

45 26484
Q:

Relation Between Efficiencies

6 boys and 8 girls finish a job in 6 days and 14 boys and 10 girls finish the same job in 4 days. In how many days working together 1 boy and 1 girl can finish the work?

Answer

Sol : In this kind of questions we find the work force required to complete the work in 1 day (or given unit of time) then we equate the work force to find the relationship between the efficiencies (or work rate) between the different workers.


 


Therefore, 6B+8G = 6 days


 => 6(6B+8G)= 1 day  (inversely proportional)


 => 36B+48G =1         ( by unitary method)


 


Again  14B+10G = 4days


 => 56B+40G =1


 


so, here it is clear that either we employ 36B and 48G to finish the work in 1 day or 56B and 40G to finish the same job in 1 day. thus , we can say


 => 36B+48G = 56B+40G


 => G= 2.5B


Thus a Girl is 2.5 times as efficient as a boy.


 


Now, since  36B+48G = 1


 => 36B+48(2.5 B)=1


 =>156B=1


i.e., to finish the job in 1 day 156 boys are required or the amount of work is 156 boys-days


 


Again    1G+1B=2.5B+1B=3.5B


 


Now, since 156 boys can finish the job in 1 day


so 1 boy can finish the job in 156 days


Therefore, 3.5 boys can finish the job in 1×1563.5= 47 days.


 


 

Report Error

View answer Workspace Report Error Discuss

Subject: Time and Work

2 3735