1
Q:

Rohit crosses a 700 metres wide road in 35 seconds. What is his speed (in km/hr)?

 

A) 54 B) 76
C) 72 D) 84

Answer:   C) 72



Explanation:
Subject: Time and Work
Exam Prep: Bank Exams
Q:

Mehdi can complete a work in 25 hours. If he is joined by Jahnavi who is 50% more efficient, in what time will they together finish the work?

A) 12 hours B) 10 hours
C) 3 hours D) 9 hours
 
Answer & Explanation Answer: B) 10 hours

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1382
Q:

A painter can paint a fence in 24 hours. After 6 hours he takes a break. What fraction of the fence is yet to be painted?

A) 0.6 B) 0.2
C) 0.75 D) 0.8
 
Answer & Explanation Answer: C) 0.75

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1244
Q:

24 men can do a piece of work in 17 days.How many men will be able to do it in 51 days ?

A) 8 B) 10
C) 12 D) 6
 
Answer & Explanation Answer: A) 8

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 996
Q:

A can do a piece of work in 8 days and B can do it in 10 days seperately. How many days would it take for both A and B to finish the same work together?

A) 33/8 B) 40/9
C) 41/10 D) 42/11
 
Answer & Explanation Answer: B) 40/9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 930
Q:

Amar is 2 times as good a workman as Badal and therefore is able to finish a job in 15 days less than Badal. In how many days can they together complete the job?

A) 30 days B) 40 days
C) 10 days D) 20 days
 
Answer & Explanation Answer: C) 10 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1480
Q:

A does 75% of a work in 50 days. He then calls in B and they together finish the remaining work in 10 days. How long B alone would take to complete the whole work?

A) 200 days B) 50 days
C) 100 days D) 125 days
 
Answer & Explanation Answer: C) 100 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

7 2116
Q:

Prabodh has done 1/2 of a job in 30 days, Sapan completes the rest of the job in 45 days. In how many days can they together do the job?

A) 18 days B) 48 days
C) 27 days D) 36 days
 
Answer & Explanation Answer: D) 36 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1722
Q:

Badki can bake 45 cakes in 9 hours, Badki and Chutki together can bake 80 cakes in 10 hours. How many cakes Chutki can bake in 40 hours?

A) 125 B) 10
C) 120 D) 20
 
Answer & Explanation Answer: C) 120

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams , CAT

0 1414