Q:
A) 5 (2/3) | B) 6 (3/4 ) |
C) 4 (1/2) | D) 3 |
Answer: C) 4 (1/2)
Explanation:
Explanation:
Work done by P alone in one day = 1/6th of the total work done by Q alone in one day = 1/3(of that done by P in one day) = 1/3(1/6 of the total) = 1/18 of the total.
Work done by P and Q, working together in one day = 1/6 + 1/18 = 4/18 = 2/9
They would take 9/2 days = 4 (1/2) days to complete the work working together.