Mr. stenley employed a certain number of typist for his project. 8 days later 20% of the typist left the job and it was found that it took as much time to complete the rest work from then as the entire work needed with all the employed typists. The average speed of a typist is 20 pages/hour. Minimum how many typist could be employed?
A) 10
B) 5
C) 15
D) 4
Answer: B) 5
Explanation:
Since 20% i.e 1/5 typists left the job. So, there can be any value which is multiple of 5 i.e, whose 20% is always an integer. Hence, 5 is the least possible value.
X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part of the total work?
P can make a table in 16 days while Q can make it in 20 days. Q started the work and did that work for 5 days. In how many days P can complete the remaining work?
Type 1 workers are 2.5 times as efficient as type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 15 Type 2 workers to do the same work?