13
Q:
| A) 120 days | B) 119 days |
| C) 118 days | D) 117 days |
Answer: D) 117 days
Explanation:
Explanation:
K's work in a day(1st day) = 1/30
L's work in a day(2nd day)= -1/60(demolishing)
hence in 2 days, combined work= 1/30 - 1/60 =1/60
since both works alternatively, K will work in odd days and L will work in even days.
1/60 unit work is done in 2 days
58/60 unit work will be done in 2 x 58 days = 116 days
Remaining work = 1-58/60 = 1/30
Next day, it will be K's turn and K will finish the remaining 1/30 work.
hence total days = 116 + 1 = 117.
Aptitude and Reasoning
General Knowledge
Puzzles
Interviews
Technical
Certifications
Exams
Job
Roles
True or False
Exams